Short answer
treat the whole job as a fixed number of units. Take the LCM of the given days as the total work, divide it by each person's days to get their work per day, add the rates of people working together, and divide the total work by the combined rate. This 'LCM method' avoids fractions and solves almost every time and work question, including pipes and cisterns, in a few lines.
The two ideas behind every question
- Work = rate × time. If A finishes a job in 12 days, A does 1/12 of it each day.
- Rates add when people work together. Two people working together do the sum of their daily work. A pipe that empties a tank has a negative rate.
The LCM method simply picks a total that every person's days divide into, so each daily rate is a whole number.
Worked example 1: two people together
A can finish a job in 12 days and B in 18 days. How long will they take together?
- Total work = LCM(12, 18) = 36 units.
- A's rate = 36 / 12 = 3 units a day. B's rate = 36 / 18 = 2 units a day.
- Together = 5 units a day, so time = 36 / 5 = 7.2 days (7 1/5 days).
Worked example 2: finding one person's time
A and B together finish a job in 10 days; A alone takes 15 days. How long does B take alone?
- Total work = LCM(10, 15) = 30 units.
- A and B together = 3 units a day; A alone = 2 units a day.
- So B = 3 − 2 = 1 unit a day, and B alone takes 30 days.
Worked example 3: three workers
A, B and C can finish a job in 20, 30 and 60 days. Working together? Total = 60 units; rates are 3, 2 and 1 units a day; together 6 units a day, so 10 days.
Worked example 4: someone leaves midway
A (12 days) and B (18 days) work together for 4 days, then A leaves. How long does the whole job take?
- Total = 36 units; A = 3 a day, B = 2 a day.
- In 4 days together they do 4 × 5 = 20 units, leaving 16 units.
- B alone finishes 16 units in 16 / 2 = 8 days.
- Whole job = 4 + 8 = 12 days.
Worked example 5: alternate days
A can finish a job in 10 days and B in 15 days. They work on alternate days, starting with A. Total = 30 units; A does 3 and B does 2, so every pair of days completes 5 units. Six pairs complete exactly 30 units, so the job takes 12 days. (If the units did not divide exactly, you would finish the last part with whoever's turn it is.)
Efficiency ratios
If A is twice as efficient as B, give them rates of 2 and 1 units a day. Example: A is twice as efficient as B and together they finish a job in 14 days. Total work = (2 + 1) × 14 = 42 units. A alone takes 42 / 2 = 21 days; B alone takes 42 / 1 = 42 days.
Man-days and man-hours
When a group of workers is involved, the total work is workers × days × hours a day, so M1 × D1 × H1 = M2 × D2 × H2 for the same job (divide each side by the work if the jobs differ).
- 10 workers can finish a job in 12 days, so the job is 120 worker-days. To finish in 8 days you need 120 / 8 = 15 workers.
- 8 workers working 9 hours a day finish in 20 days: 8 × 9 × 20 = 1,440 worker-hours. 12 workers working 8 hours a day (96 worker-hours a day) need 1,440 / 96 = 15 days.
Sharing wages
Wages are shared in the ratio of work done, not time spent. Example: A (12 days) and B (18 days) do a job together and are paid 4,500. Their rates are 3 : 2 and they worked the same days, so A gets 4,500 × 3/5 = 2,700 and B gets 1,800.
Pipes and cisterns
Pipes are the same idea: a filling pipe has a positive rate, an emptying pipe a negative one. Example: pipe A fills a tank in 6 hours, pipe B in 8 hours, and pipe C empties it in 12 hours. With all three open, how long to fill it?
- Tank = LCM(6, 8, 12) = 24 units.
- A = +4, B = +3, C = −2 units an hour; net = +5 units an hour.
- Time = 24 / 5 = 4.8 hours = 4 hours 48 minutes.
| Situation | What to do |
|---|---|
| Two or more people together | Take the LCM of their days as total work; add daily rates |
| One person's time from a joint time | Subtract the known rate from the joint rate |
| Someone leaves or joins | Split the work into stages and subtract what is already done |
| Efficiency given as a ratio | Use the ratio numbers as daily rates |
| Groups of workers | Workers × days × hours is constant for the same job |
| Wages | Share in the ratio of work done |
| Pipes and cisterns | Emptying pipes have negative rates |
Common mistakes
- Adding days instead of rates (A in 12 days and B in 18 days does not mean 30 days together).
- Forgetting to subtract work already done when someone leaves.
- Giving an emptying pipe a positive rate.
- Sharing wages by days worked when the workers have different efficiencies.
Learn and practise on Sikhora
Take the free time and work foundation course, then the practice course and the advanced course. The same rate idea powers time, speed and distance, a good topic to learn next.
Course · Beginner · Free
Quantitative Aptitude — Time and Work: Foundation
Foundation course on Time and Work (Quantitative Aptitude): the basics, explained from the start.
Related
- Quantitative Aptitude — Time and Work: Foundation · Course
- Quantitative Aptitude — Time and Work: Practice · Course
- Quantitative Aptitude — Time and Work: Advanced · Course
- Time and Work: topic test (Quantitative Aptitude) · Test
- Quantitative Aptitude · Subject
- Lokrakshak Cadre Recruitment (Gujarat Police) · Exam
Related
- Quantitative Aptitude — Time Speed and Distance: Foundation · Course
- Quantitative Aptitude — Time Speed and Distance: Practice · Course
- Quantitative Aptitude — Time Speed and Distance: Advanced · Course
- Time Speed and Distance: topic test (Quantitative Aptitude) · Test
- Quantitative Aptitude · Subject
- Lokrakshak Cadre Recruitment (Gujarat Police) · Exam
Practise time and work questions against the clock.
Take a practice testFrequently asked questions
What is the LCM method in time and work?
Take the LCM of the given days as the total work in units. Each person's daily work is the total divided by their days. Add rates for people working together, then divide the total by the combined rate.
If A takes 12 days and B takes 18 days, how long together?
With 36 units of work, A does 3 and B does 2 units a day. Together they do 5 a day, so 36 / 5 = 7.2 days.
How are wages divided in time and work questions?
In the ratio of work done. If two people work the same number of days, that is the ratio of their efficiencies.
How are pipes and cisterns related to time and work?
They are the same method. A filling pipe has a positive rate and an emptying pipe has a negative rate; add the rates and divide the tank's capacity by the net rate.
What does 'twice as efficient' mean?
It means doing twice as much work per day, so taking half the time. Give the rates as 2 and 1 units a day.
What is the man-days formula?
For the same job, workers × days × hours per day stays constant: M1 × D1 × H1 = M2 × D2 × H2.