Cabinet approves Green Energy Corridor Phase-III
Last checked against its source:
The Union Cabinet approved the Green Energy Corridor Phase-III (GEC-III) scheme to strengthen intra-state transmission systems so that up to 135 GW of renewable energy can be evacuated across States and Union Territories. The scheme also provides for 50 GWh of Battery Energy Storage Systems. It is targeted for completion by FY 2032-33, with a total project outlay of Rs 1,86,405 crore and Central Financial Support of Rs 54,082 crore. State Transmission Utilities will be the overall implementing agencies.
Test yourself
-
1. Green Energy Corridor Phase-III will enable evacuation of up to how much renewable energy?
- 50 GW
- 135 GW
- 500 GW
- 900 GW
Show answer
Answer: B. The scheme strengthens intra-state transmission to evacuate up to 135 GW of renewable energy.
-
2. How much Battery Energy Storage System capacity does GEC-III provide for?
- 10 GWh
- 25 GWh
- 50 GWh
- 135 GWh
Show answer
Answer: C. The scheme provides for deployment of 50 GWh of Battery Energy Storage Systems.
-
3. By when is the Green Energy Corridor Phase-III scheme targeted to be set up?
- FY 2027-28
- FY 2029-30
- FY 2032-33
- FY 2035-36
Show answer
Answer: C. The scheme is targeted to be set up by FY 2032-33.