Work Energy and Power

Practice questions

A 1 kg block is projected up a 30° incline at 8 m/s with a constant friction force of 3 N. It returns to its starting point with speed (g = 10 m/s²):

  1. 8 m/s
  2. 6 m/s
  3. 4 m/s
  4. 2 m/s
Answer and explanation

Answer: C

It travels up 4 m, since 8d = 32 J. Coming down, KE = 5 × 4 − 3 × 4 = 8 J, so v = 4 m/s.

A spring storing 2 J launches a 1 kg block over a horizontal surface with a friction force of 2 N. The block travels:

  1. 0.5 m
  2. 2 m
  3. 4 m
  4. 1 m
Answer and explanation

Answer: D

Friction work 2 × d equals the stored energy 2 J, so d = 1 m.

A ball dropped from 10 m rebounds to 6 m. The percentage of its mechanical energy lost in the bounce is:

  1. 6%
  2. 40%
  3. 60%
  4. 4%
Answer and explanation

Answer: B

Energy is proportional to height, so the loss is (10 − 6)/10 = 40%.

A car at 10 m/s skids to rest on a road with μ = 0.25 (g = 10 m/s²). The skid distance is:

  1. 10 m
  2. 50 m
  3. 40 m
  4. 20 m
Answer and explanation

Answer: D

d = v² ÷ (2μg) = 100 ÷ (2 × 0.25 × 10) = 100 ÷ 5 = 20 m.

A 2 kg block slides from rest 4 m down a 30° incline against a friction force of 6 N (g = 10 m/s²). Its speed at the bottom is:

  1. 4 m/s
  2. 2 m/s
  3. 8 m/s
  4. 6 m/s
Answer and explanation

Answer: A

PE lost = 2 × 10 × 2 = 40 J. Friction work = 24 J. KE = 16 J, so v = 4 m/s.

A 1000 kg car, with no resistance, is accelerated from rest by a constant force of 2000 N. The power at t = 5 s is:

  1. 4 kW
  2. 10 kW
  3. 40 kW
  4. 20 kW
Answer and explanation

Answer: D

a = 2 m/s², so v = 10 m/s at 5 s. P = F v = 2000 × 10 = 20 kW.

A 750 W iron is used for 4 hours. The energy used is:

  1. 3 kWh
  2. 750 kWh
  3. 0.19 kWh
  4. 30 kWh
Answer and explanation

Answer: A

Energy = 0.75 kW × 4 h = 3 kWh.

An engine delivering 30 kW moves a car at a steady 15 m/s. The driving force is:

  1. 450 N
  2. 2 N
  3. 4500 N
  4. 2000 N
Answer and explanation

Answer: D

F = P ÷ v = 30 000 ÷ 15 = 2000 N.

A pump delivers 3 kW of useful power and has an efficiency of 75%. Its input power is:

  1. 2.25 kW
  2. 4 kW
  3. 3 kW
  4. 3.75 kW
Answer and explanation

Answer: B

Input = output ÷ efficiency = 3 ÷ 0.75 = 4 kW.

A crane lifts a 400 kg load at a steady speed of 3 m/s (g = 10 m/s²). The power needed is:

  1. 1.2 kW
  2. 4 kW
  3. 12 kW
  4. 120 kW
Answer and explanation

Answer: C

F = mg = 4000 N. P = F v = 4000 × 3 = 12 000 W = 12 kW.

A 1 kg block is dropped from 0.4 m above a spring of constant 1000 N/m (g = 10 m/s²). The maximum compression of the spring is:

  1. 0.2 m
  2. 0.1 m
  3. 0.04 m
  4. 0.4 m
Answer and explanation

Answer: B

mg(0.4 + x) = ½ k x² gives 500x² − 10x − 4 = 0, with positive root x = 0.1 m.

A ball is thrown at 20 m/s at 30° above the horizontal. Its speed at the highest point is about:

  1. about 10 m/s
  2. about 20 m/s
  3. zero
  4. about 17 m/s
Answer and explanation

Answer: D

At the top, only the horizontal component remains: 20 cos 30° ≈ 17.3 m/s.

A ball is thrown at 10 m/s from a height of 15 m in some direction. It reaches the ground with speed (g = 10 m/s²):

  1. 20 m/s
  2. 25 m/s
  3. 15 m/s
  4. depends on the direction
Answer and explanation

Answer: A

v² = u² + 2gh = 100 + 300 = 400, so v = 20 m/s, whatever the direction of throw.

A 0.5 kg bob on a 0.8 m string is released from the horizontal. At the lowest point the tension in the string is:

  1. 5 N
  2. 10 N
  3. 20 N
  4. 15 N
Answer and explanation

Answer: D

v² = 2gl = 16. T = mg + mv²/l = 5 + 0.5 × 16 ÷ 0.8 = 5 + 10 = 15 N.

A body slides from rest down a smooth slope from a height of 3.2 m (g = 10 m/s²). Its speed at the bottom is:

  1. 6.4 m/s
  2. 16 m/s
  3. 8 m/s
  4. 4 m/s
Answer and explanation

Answer: C

v = √(2gh) = √(2 × 10 × 3.2) = √64 = 8 m/s.

A 2 kg block at rest gains 16 J of kinetic energy from a variable force. Its speed is:

  1. 8 m/s
  2. 4 m/s
  3. 16 m/s
  4. 2 m/s
Answer and explanation

Answer: B

½ × 2 × v² = 16, so v² = 16 and v = 4 m/s.

A force F = (2x + 1) N acts through a displacement from x = 0 to x = 3 m. The work done is:

  1. 7 J
  2. 21 J
  3. 12 J
  4. 9 J
Answer and explanation

Answer: C

The force rises from 1 N to 7 N, so the work is the area of the trapezium: ½ × (1 + 7) × 3 = 12 J.

A spring of constant 300 N/m is stretched from 5 cm to 15 cm. The work done is:

  1. 1.5 J
  2. 6.75 J
  3. 0.3 J
  4. 3 J
Answer and explanation

Answer: D

W = ½ × 300 × (0.15² − 0.05²) = 150 × 0.02 = 3 J.

A force of +8 N acts for 2 m, then −4 N for the next 3 m. The net work is:

  1. 4 J
  2. 28 J
  3. 12 J
  4. 16 J
Answer and explanation

Answer: A

8 × 2 = 16 J and −4 × 3 = −12 J. The total is 4 J.

A force rises uniformly from 0 to 10 N over a displacement of 6 m. The work done is:

  1. 60 J
  2. 30 J
  3. 15 J
  4. 10 J
Answer and explanation

Answer: B

The graph is a triangle: ½ × 6 × 10 = 30 J.