Time and Work

Practice questions

A is twice as efficient as B. Together they finish a job in 12 days. How long does B take alone?

  1. 24 days
  2. 18 days
  3. 36 days
  4. 48 days
Answer and explanation

Answer: C

A does 2 parts and B does 1 part a day, so the job is 36 parts. B does 1 part a day and takes 36 days.

Eighteen men finish a job in 25 days. How many days will 30 men take?

  1. 15 days
  2. 10 days
  3. 20 days
  4. 30 days
Answer and explanation

Answer: A

Total 18 × 25 = 450 man-days; 450 ÷ 30 = 15 days.

An inlet fills a tank in 10 hours and an outlet empties it in 15 hours. With both open, how long to fill the empty tank?

  1. 25 hours
  2. 6 hours
  3. 12 hours
  4. 30 hours
Answer and explanation

Answer: D

With 30 units: inlet 3, outlet 2, net 1 an hour, so 30 hours.

A takes 15 days and B takes 30 days. They start together and A leaves after 5 days. How long does the job take in all?

  1. 10 days
  2. 20 days
  3. 15 days
  4. 25 days
Answer and explanation

Answer: B

With 30 units: A does 2, B does 1; 5 days give 15 units; B does the other 15 in 15 days; total 20 days.

A takes 6 days and B takes 12 days. How long do they take together?

  1. 3 days
  2. 9 days
  3. 6 days
  4. 4 days
Answer and explanation

Answer: D

With 12 units, A does 2 and B does 1, so 3 a day: 12 ÷ 3 = 4 days.

A takes 12 days and B takes 8 days. They work on alternate days, A first. How long do they take?

  1. 10 days
  2. 9 2/3 days
  3. 9 1/3 days
  4. 9 days
Answer and explanation

Answer: B

With 24 units, each 2-day cycle gives 5 units. After 8 days there are 20; day 9 gives 22; B needs 2/3 of day 10. The total is 9 2/3 days.

A pipe fills a tank in 6 hours and a leak empties the full tank in 10 hours. How long to fill the empty tank?

  1. 4 hours
  2. 16 hours
  3. 15 hours
  4. 3.75 hours
Answer and explanation

Answer: C

With 30 units: 5 − 3 = 2 per hour, so 30 ÷ 2 = 15 hours.

Ten men working 6 hours a day take 12 days. How long will they take working 8 hours a day?

  1. 9 days
  2. 10 days
  3. 12 days
  4. 16 days
Answer and explanation

Answer: A

10 × 6 × 12 = 720 man-hours; 720 ÷ (10 × 8) = 9 days.

A takes 20 days and B takes 30 days. They work together, but A leaves 5 days before the work is finished. How long does the work take in all?

  1. 15 days
  2. 12 days
  3. 20 days
  4. 18 days
Answer and explanation

Answer: A

(t − 5)/20 + t/30 = 1 gives 5t = 75, so t = 15 days.

A takes 10 days and B takes 15 days. How long do they take together?

  1. 12.5 days
  2. 25 days
  3. 6 days
  4. 5 days
Answer and explanation

Answer: C

1/10 + 1/15 = 1/6, so they take 6 days.

A worker normally needs 40 days. For the first 10 days he works at 80% efficiency, then at full efficiency. How many days in all?

  1. 40 days
  2. 42 days
  3. 45 days
  4. 50 days
Answer and explanation

Answer: B

10 days at 80% equal 8 normal days. 32 normal days remain, so the total is 10 + 32 = 42 days.

A is 60% as efficient as B, and B takes 15 days. How long does A take?

  1. 9 days
  2. 20 days
  3. 30 days
  4. 25 days
Answer and explanation

Answer: D

A : B = 3 : 5 in efficiency, so the time ratio is 5 : 3. A takes 15 × 5/3 = 25 days.

If a worker's efficiency falls by 20%, by what percentage does the time for the same job increase?

  1. 20%
  2. 25%
  3. 15%
  4. 30%
Answer and explanation

Answer: B

New time = 100/80 = 125% of the old time, an increase of 25%.

If a worker's efficiency increases by 25%, by what percentage does the time for the same job decrease?

  1. 25%
  2. 30%
  3. 15%
  4. 20%
Answer and explanation

Answer: D

New time = 100/125 = 80% of the old time, so it decreases by 20%.

A is 20% more efficient than B. B takes 24 days. How long does A take?

  1. 20 days
  2. 18 days
  3. 19.2 days
  4. 28.8 days
Answer and explanation

Answer: A

Efficiency A : B = 6 : 5, so time A : B = 5 : 6. Time for A = 24 × 5/6 = 20 days.

A, B and C together take 6 days. A and B alone take 10 days. How long does C take alone?

  1. 4 days
  2. 12 days
  3. 15 days
  4. 16 days
Answer and explanation

Answer: C

1/6 − 1/10 = 5/30 − 3/30 = 2/30 = 1/15, so C takes 15 days.

A+B take 18 days, B+C take 24 days, C+A take 36 days. How long do all three take together?

  1. 12 days
  2. 18 days
  3. 16 days
  4. 20 days
Answer and explanation

Answer: C

With 72 units the pair rates are 4, 3, 2. Sum 9, half 4.5, and 72 ÷ 4.5 = 16 days.

A+B take 10 days, B+C take 15 days, C+A take 12 days. How long do all three take together?

  1. 8 days
  2. 7 days
  3. 9 days
  4. 12 days
Answer and explanation

Answer: A

With 60 units the pair rates are 6, 4, 5. Sum 15, half 7.5, and 60 ÷ 7.5 = 8 days.

A+B take 12 days, B+C take 15 days, C+A take 20 days. How long do all three take together?

  1. 9 days
  2. 12 days
  3. 8 days
  4. 10 days
Answer and explanation

Answer: D

The pair rates 5, 4, 3 sum to 12 units a day; half is 6; 60 ÷ 6 = 10 days.

A+B take 12 days, B+C take 15 days, C+A take 20 days. How long does A take alone?

  1. 24 days
  2. 30 days
  3. 20 days
  4. 60 days
Answer and explanation

Answer: B

With 60 units the pairs do 5, 4, 3, so all three do 6. A = 6 − 4 = 2 units a day, so 60 ÷ 2 = 30 days.