The corner-point method always works, but with five or six corners it is slow and every extra calculation is a chance to slip. This lesson adds two faster tools: the iso-profit line method, which shows where the optimum must be, and the slope ladder, which turns that picture into a quick comparison of numbers. Use them to choose the likely corner, then confirm with one or two evaluations.
Iso-profit and iso-cost lines
For Z = px + qy, every line px + qy = k is an iso-profit line (or iso-cost line in a minimisation): all its points give the same Z. These lines are parallel, with slope −p/q. Draw one through the region, then slide it parallel to itself: away from the origin to increase Z (when p and q are positive), towards it to decrease Z. The last point of the region it touches is the optimum.
The slope ladder
Walk round the boundary of a region bounded by ≤ constraints, from the top of the y-axis to the right end of the x-axis. The edge slopes get steeper and steeper. For a maximum with p, q > 0, the optimal corner is where the objective's slope −p/q fits between the slopes of the two edges meeting there.
Worked example 1: the lamp problem solved
Maximise Z = 50x + 60y subject to x + 3y ≤ 24, 3x + 2y ≤ 24, x + y ≤ 10, x, y ≥ 0 (from lesson 1). The corners, in order round the boundary, are (0, 8), (3, 7), (4, 6) and (8, 0), plus the origin.
| Edge | Line | Slope | Joins |
|---|---|---|---|
| first | x + 3y = 24 | −1/3 | (0, 8) to (3, 7) |
| second | x + y = 10 | −1 | (3, 7) to (4, 6) |
| third | 3x + 2y = 24 | −3/2 | (4, 6) to (8, 0) |
The objective's slope is −50/60 = −5/6 ≈ −0.83. It lies between −1/3 and −1, so the optimum is at the corner joining those edges, (3, 7). Confirm: Z(3, 7) = 150 + 420 = 570, against 560 at (4, 6) and 480 at (0, 8). Make 3 Standard and 7 Deluxe lamps for ₹570. The ladder also tells you at once that Z = 5x + 4y (slope −1.25) would be best at (4, 6), and Z = 2x + y (slope −2) at (8, 0).
For a maximum with p, q > 0 on a region bounded by ≤ constraints, the optimal corner is where the slope −p/q of the objective lies between the slopes of the two edges that meet there.
Speed tool: Cramer's rule for corners
For a₁x + b₁y = c₁ and a₂x + b₂y = c₂, let D = a₁b₂ − a₂b₁. Then x = (c₁b₂ − c₂b₁)/D and y = (a₁c₂ − a₂c₁)/D. For 2x + 3y = 18 and 5x + 4y = 31: D = 8 − 15 = −7, x = (72 − 93)/(−7) = 3, y = (62 − 90)/(−7) = 4. So the lines meet at (3, 4).
Worked example 2: scaling and skipping corners
Maximise Z = 120x + 150y subject to 2x + 3y ≤ 18, 5x + 4y ≤ 31, x ≤ 5, x, y ≥ 0. First scale: Z = 30(4x + 5y), so compare 4x + 5y. The corners are (0, 0), (5, 0), (5, 3/2) where x = 5 meets 5x + 4y = 31, (3, 4) and (0, 6). With positive coefficients, a corner that another corner beats in both coordinates cannot win: (0, 0) and (5, 0) are beaten by (5, 3/2). Compare the rest: 4x + 5y = 27.5, 32 and 30. The maximum is at (3, 4): Z = 30 × 32 = 960.
Worked example 3: when the iso-profit line lies along an edge
On the region of example 2, maximise Z = 6x + 9y. Its slope is −6/9 = −2/3, exactly the slope of the edge 2x + 3y = 18. Since Z = 3(2x + 3y) ≤ 3 × 18 = 54, the sliding iso-profit line leaves the region along that whole edge: (3, 4) and (0, 6) both give 54, and so does every point between them. When −p/q equals an edge slope, expect a whole edge of optimal points (lesson 5).
Key takeaways: iso-profit lines are parallel with slope −p/q; slide them to find the optimum. Compare −p/q with the edge slopes to pick the corner, scale Z to small numbers, skip corners that are beaten in both coordinates, and confirm with a quick evaluation.
Check your understanding
-
1. The region x + 2y ≤ 16, x + y ≤ 10, 2x + y ≤ 16, x, y ≥ 0 has corners (0, 0), (8, 0), (6, 4), (4, 6) and (0, 8). At which corner is Z = 3x + 4y largest?
- (6, 4)
- (4, 6)
- (0, 8)
- (8, 0)
Show answer
Answer: B. Slope of Z: −3/4. The corner (4, 6) joins edges of slope −1/2 (x + 2y = 16) and −1 (x + y = 10), and −3/4 lies between them, so (4, 6) is optimal. Check: Z = 36 there, against 34 at (6, 4), 32 at (0, 8) and 24 at (8, 0).
-
2. On the same region, what is the maximum of Z = 5x + 2y?
- 38
- 32
- 50
- 40
Show answer
Answer: D. Slope −5/2 is steeper than −2, the steepest edge (2x + y = 16), so the optimum is at the end of that edge on the x-axis, (8, 0): Z = 40. (6, 4) gives 38 and (4, 6) gives 32. 50 comes from (10, 0), which breaks 2x + y ≤ 16.
-
3. Where do the lines 3x + 4y = 25 and 5x − 2y = 7 meet?
- (3, 4)
- (4, 3)
- (5, 9/2)
- (1, 11/2)
Show answer
Answer: A. Cramer's rule: D = 3(−2) − 5(4) = −26. x = (25(−2) − 7(4))/(−26) = −78/(−26) = 3. y = (3(7) − 5(25))/(−26) = −104/(−26) = 4. Check: 9 + 16 = 25 and 15 − 8 = 7.
-
4. Maximise Z = 150x + 250y subject to x + 2y ≤ 10, 3x + 2y ≤ 18, x, y ≥ 0. What is the maximum?
- 27
- 1250
- 1350
- 900
Show answer
Answer: C. Z = 50(3x + 5y). Corners (0, 0), (6, 0), (4, 3), (0, 5) give 3x + 5y = 0, 18, 27, 25. The largest is 27 at (4, 3), so Z = 50 × 27 = 1350. Answering 27 forgets to multiply back; 1250 is the value at (0, 5).
-
5. All the iso-profit lines of Z = 4x + 6y have slope:
- −3/2
- 2/3
- 3/2
- −2/3
Show answer
Answer: D. 4x + 6y = k gives y = −(4/6)x + k/6, so the slope is −p/q = −4/6 = −2/3 whatever the value of k. Changing k only shifts the line parallel to itself.