Target averages and averages over days and months
Work out the score needed in the next test to reach a target average, and find the missing figure in daily, weekly or monthly data.
If something looks wrong, please tell us.
Everyday data usually comes in a sequence: marks in successive tests, sales on each day of a week, rainfall in each month. Two questions come up again and again. How much do I need next time to reach a target average? And if I know the overall average and part of the data, what is the average of the rest? Both are answered by the same tool: totals.
Working with a target
- Target total = target average × number of periods.
- Needed amount = target total − total so far.
- If the target is an 'at least' condition, the needed amount is the least value that works.
Worked example 1: marks in tests
A student scored 72, 68, 80 and 76 in four tests. What must she score in the fifth test to have an average of 75? Target total = 75 × 5 = 375. Marks so far = 72 + 68 + 80 + 76 = 296. Needed = 375 − 296 = 79. Check: 296 + 79 = 375 and 375 ÷ 5 = 75.
Worked example 2: part of a week
A shop's average daily sales over a week of 7 days are ₹6,000. For Monday to Thursday (4 days) the average was ₹5,250. Find the average for Friday to Sunday. Total for the week = 7 × 6,000 = 42,000. Total for Monday to Thursday = 4 × 5,250 = 21,000. Total for Friday to Sunday = 42,000 − 21,000 = 21,000. Average for the 3 days = 21,000 ÷ 3 = ₹7,000. Notice that you divide by the number of days in that part, 3, not 7.
Worked example 3: temperature
The temperatures on six days were 31, 33, 30, 34, 32 and 31 degrees Celsius. What must the seventh day's temperature be for a weekly average of 32 degrees? Target total = 7 × 32 = 224. Total so far = 31 + 33 + 30 + 34 + 32 + 31 = 191. Needed = 224 − 191 = 33 degrees.
Worked example 4: rainfall over months
The average rainfall for three months is 120 mm. How much rain is needed in the fourth month to bring the four-month average up to 130 mm? Total for three months = 360. Target total = 4 × 130 = 520. Needed = 520 − 360 = 160 mm. The fourth month is 40 mm above the new average of 130, and that extra 40 is shared equally among the 4 months, raising the average by 10.
Common traps
- Dividing the total of a part by the wrong number of periods.
- Mixing up the old count and the new count when a period is added.
- Forgetting that a target can sometimes be impossible, such as needing more than the maximum score.
Needed value = (target average × total number of periods) − total so far.
Key takeaways
- Convert every average to a total before comparing.
- Subtract the known totals from the target total to find what is missing.
- Divide the missing total by the number of periods it covers to get its average.
- Check your answer by recomputing the overall average.
Check your understanding
-
1. A student scored 60, 70 and 80 in three tests. What must be scored in the fourth to make the average 75?
- 85
- 95
- 80
- 90
Show answer
Answer: D. Target total = 4 × 75 = 300. Marks so far = 210. Needed = 300 − 210 = 90.
-
2. The average over 7 days is 50. The average of the first 3 days is 46. What is the average of the remaining 4 days?
- 54
- 50
- 53
- 52
Show answer
Answer: C. Total = 350 and the first three days total 138. The remaining 4 days total 212, and 212 ÷ 4 = 53.
-
3. The average rainfall for three months is 80 mm. How much is needed in the fourth month for a four-month average of 90 mm?
- 100 mm
- 120 mm
- 90 mm
- 110 mm
Show answer
Answer: B. Target total = 360 and the total so far is 240. Needed = 120 mm.
-
4. The average temperature of 6 days is 31.5 degrees. What must the seventh day's temperature be for a weekly average of 32 degrees?
- 35 degrees
- 34 degrees
- 32 degrees
- 36 degrees
Show answer
Answer: A. Total so far = 6 × 31.5 = 189. Target total = 7 × 32 = 224. Needed = 224 − 189 = 35.
-
5. A student's average in 5 tests is 68. What must she score in the sixth test to make the average 70?
- 76
- 78
- 80
- 82
Show answer
Answer: C. Target total = 6 × 70 = 420. Total so far = 5 × 68 = 340. Needed = 420 − 340 = 80.