• Advanced
  • About 14 min
  • 5 practice questions

The units method: combined work and three-person problems

Assume the total work equals the LCM of the days, turn each person into units per day, and solve two-person and three-person problems quickly.

If something looks wrong, please tell us.

The fastest way to solve time and work problems is to avoid fractions. Choose the total work as the LCM of all the day counts. Each person then works a whole number of units per day, and adding or subtracting rates becomes plain arithmetic.

Method

  1. Take total work = LCM of the given days.
  2. Units per day of a person = total work / days that person needs.
  3. Add rates for people working together, subtract for someone who undoes the work.
  4. Days taken = total work / combined rate.

Worked example 1

A alone can finish a job in 12 days and B alone in 15 days. Total work = LCM(12, 15) = 60 units. A does 5 per day and B does 4 per day, together 9 per day. Time = 60/9 = 6 2/3 days.

Worked example 2: finding one person

A and B together finish in 10 days and B alone takes 15 days. Take 30 units: A + B = 3 per day, B = 2 per day, so A = 1 per day. A alone takes 30 days.

Worked example 3: three persons, pairs given

A and B take 12 days, B and C take 15 days, C and A take 20 days. Total work = 60. A + B = 5 per day, B + C = 4, C + A = 3. Adding: 2(A + B + C) = 12, so A + B + C = 6 per day. All three together take 60/6 = 10 days. Individually: A = 6 - 4 = 2, B = 6 - 3 = 3, C = 6 - 5 = 1 per day.

Total work = LCM of days. Combined time = total work / sum of daily units. For pairs, the sum of all three = (sum of the pair rates)/2.

— Method to remember

Key takeaways

  • Pick total work as the LCM of the days to avoid fractions.
  • Rates add when people work together.
  • For pair data, add the pair rates and halve.
  • A person's days = total work / their units per day.

Check your understanding

  1. 1. A alone can finish a job in 24 days and B alone in 40 days. Using the units method, how long do they take together?

    1. 15 days
    2. 16 days
    3. 32 days
    4. 12 days
    Show answer

    Answer: A. Total work = LCM(24, 40) = 120 units. A does 120/24 = 5 and B does 120/40 = 3 units a day, together 8. Time = 120/8 = 15 days.

  2. 2. A takes 12 days and B takes 16 days to finish a job alone. How long do they take working together?

    1. 7 days
    2. 14 days
    3. 6 1/2 days
    4. 6 6/7 days
    Show answer

    Answer: D. Total work = LCM(12, 16) = 48 units. A does 4 and B does 3 a day, together 7. Time = 48/7 = 6 6/7 days.

  3. 3. A and B together finish a job in 15 days and B alone takes 20 days. How long does A alone take?

    1. 35 days
    2. 40 days
    3. 60 days
    4. 45 days
    Show answer

    Answer: C. Take 60 units. A + B = 60/15 = 4 a day and B = 60/20 = 3 a day, so A = 1 a day. A alone takes 60 days.

  4. 4. A and B take 9 days, B and C take 12 days, and C and A take 18 days. How long do A, B and C take together?

    1. 6 days
    2. 8 days
    3. 9 days
    4. 12 days
    Show answer

    Answer: B. Total = LCM(9, 12, 18) = 36 units. Pair rates: 4, 3 and 2 a day. Their sum 9 counts each person twice, so A + B + C = 4.5 a day. Time = 36/4.5 = 8 days.

  5. 5. A and B take 9 days, B and C take 12 days, and C and A take 18 days. How long would C alone take?

    1. 36 days
    2. 48 days
    3. 54 days
    4. 72 days
    Show answer

    Answer: D. With 36 units: A + B = 4, B + C = 3, C + A = 2, so A + B + C = 9/2 = 4.5 a day. C = (A + B + C) - (A + B) = 4.5 - 4 = 0.5 a day. C alone takes 36/0.5 = 72 days.