• Practice
  • About 14 min
  • 5 practice questions

Rivers and power: projects, tributaries and hazards

Revise the Teesta system, match hydroelectric projects with their rivers, do simple power and energy sums, and link floods and glacial lakes with the risk to projects.

If something looks wrong, please tell us.

Questions on power in Sikkim reward students who connect geography and economy. The rivers decide where projects stand, and the same rivers decide where floods strike. This lesson revises the river system, the projects and the hazards in one chain.

The river chain

The Teesta rises in North Sikkim. At Chungthang the Lachen Chu and Lachung Chu meet to form the main river. The Teesta runs south through the state, is joined by the Rangit near the border with West Bengal, enters the plains, flows through Bangladesh and joins the Brahmaputra. Questions often give a place name and ask which river it belongs to, so tie each place to a stream.

Revision table: places, rivers and projects
Place or projectRiver or linkRegion
ChungthangMeeting of Lachen Chu and Lachung ChuNorth Sikkim
Teesta IIITeesta at ChungthangNorth Sikkim
Teesta VTeesta, near DikchuEast Sikkim
Rangit projectRangit riverWest and South Sikkim
RangpoLower Teesta valley, industrial townEast Sikkim, near West Bengal

Where the Teesta system flows

  1. Tso Lhamo and glaciers Source area in North Sikkim
  2. Lachen Chu and Lachung Chu Meet at Chungthang
  3. Teesta valley Flows south through projects and towns
  4. Rangit joins Near the West Bengal border
  5. Bangladesh and Brahmaputra Out of India and into the Jamuna
The journey of the Teesta

Power sums made simple

Exams sometimes use an illustrative sum. Power is measured in megawatts (MW) and energy in megawatt hours (MWh). Energy equals power multiplied by time. If a station works at 100 MW for 5 hours, it produces 100 times 5, which is 500 MWh. Do not confuse the two units: MW is the rate, MWh is the amount.

Hazards for projects

  • Glacial lake outburst. A lake held back by ice or loose rock bursts and sends a flood downstream. In October 2023 an outburst from South Lhonak lake in North Sikkim sent a flood down the Teesta valley, and the dam at Chungthang was among the structures damaged.
  • Landslides. Tunnels and roads cut into young slopes can trigger slides in heavy rain.
  • Earthquakes. The Himalaya is young and still rising, so structures must be built to resist shaking.
  • Silt. Fast mountain rivers carry stones and sand that can wear out turbines.

Reading a river question

When a river question appears, draw a quick line sketch on rough paper: north at the top, the Teesta running down the middle, the Lachen Chu and Lachung Chu joining at the upper end, and the Rangit entering from the west near the bottom. Mark each project on the sketch. A thirty-second sketch turns a vague memory into a picture, and a picture is much harder to forget in the exam hall. Check the sketch against the table before you answer.

Worked examples

Example 1. 'At which place do the Lachen Chu and Lachung Chu meet?' Answer: Chungthang.

Example 2. 'A station generates 60 MW for 8 hours. How much energy does it produce?' 60 times 8 equals 480 MWh.

Example 3. 'Which is the largest tributary of the Teesta in Sikkim?' From the geography lessons, it is the Rangit.

Example 4. 'Why can a dam be damaged by a glacial lake outburst far upstream?' The flood travels down the river valley, so a dam downstream meets a sudden surge of water, rock and silt. The danger is greatest on a river fed by glaciers.

Chungthang = Lachen Chu + Lachung Chu. Rangit = biggest tributary. Energy (MWh) = power (MW) x hours.

Key takeaways: Tie each project to its river and region. Use the formula for energy in sums. Link glacial lake outburst floods with the risk to the dams and bridges of the Teesta valley.

Check your understanding

  1. 1. Where do the Lachen Chu and Lachung Chu meet?

    1. Rangpo
    2. Chungthang
    3. Pakyong
    4. Gangtok
    Show answer

    Answer: B. The two streams meet at Chungthang to form the Teesta.

  2. 2. A station produces 25 MW for 4 hours. What is the energy?

    1. 29 MWh
    2. 6.25 MWh
    3. 21 MWh
    4. 100 MWh
    Show answer

    Answer: D. Energy is power times time: 25 times 4 equals 100 MWh.

  3. 3. Which project is on the Rangit river?

    1. Teesta V
    2. Teesta III
    3. Nathu La mart
    4. The Rangit hydroelectric project
    Show answer

    Answer: D. The Rangit project stands on the Rangit river.

  4. 4. Which hazard damaged structures in the Teesta valley in October 2023?

    1. A volcanic eruption
    2. A glacial lake outburst flood
    3. A cyclone from the sea
    4. A drought
    Show answer

    Answer: B. An outburst from South Lhonak lake sent a flood down the valley.

  5. 5. Which unit measures energy, not power?

    1. Megawatt hour
    2. Megawatt
    3. Kilowatt
    4. Watt
    Show answer

    Answer: A. A megawatt hour is a quantity of energy; the others are rates of power.