A state with steep, fast rivers has power on its doorstep. Sikkim's rivers have been used for hydroelectric projects, and questions about them test both names and understanding. This lesson helps you revise both without needing numbers.
How a project is built
Parts of a hydroelectric scheme
- Dam or barrage Raises the river and diverts water
- Intake and tunnel Carries water through the hill
- Penstock A steep pipe that drops the water
- Turbine and generator Spin and make electricity
- Tailrace Returns water to the river
A run-of-the-river project takes the water that is flowing and returns it a short distance downstream, with little storage. A storage project holds a large reservoir. In steep Himalayan valleys, many projects are run-of-the-river, because the fall of the river gives the power.
Projects to recognise
| Project | River | Memory hook |
|---|---|---|
| Teesta III | Teesta, near Chungthang | Upper Teesta |
| Teesta V | Teesta, lower down | Further south than Teesta III |
| Dikchu | Dikchu stream | Named after the stream and the town |
| Rangit | Rangit | Western river |
Project names change with companies and stages, so stay with the river and the place. If a question asks which river carries the Teesta III project, the answer is the Teesta. If it asks about a project of the Rangit, the answer is the Rangit.
Advantages and concerns
| Advantages | Concerns |
|---|---|
| Clean power without burning fuel | Tunnels and roads on young, loose slopes can cause landslides |
| Uses a renewable resource | Dams alter the natural flow of the river |
| Work and income for local people | Forest land and village land may be affected |
| Power can be sent to other states | Floods can damage a project, as seen at Chungthang in 2023 |
Worked example 1. Question: 'Why are most Himalayan hydro projects run-of-the-river?' Working: the steep fall of the river already supplies the head for power, so a large reservoir is not needed. Answer: steep fall gives the power.
Worked example 2. Question: 'Which river carries the Dikchu project?' Working: the project is named after the Dikchu stream and takes its water. Answer: the Dikchu.
Worked example 3. Question: 'Name one concern about building tunnels and roads for dams in Sikkim.' Working: Sikkim's slopes are young and loose, so excavation can trigger landslides. Answer: landslides.
Water has other uses too: drinking water from springs, irrigation for terraces and tourism at lakes and hot springs. Hydropower is one use among many, and balanced answers mention both benefit and care.
Question types to expect
- Name-the-river: 'The project at Chungthang uses which river?'
- Reason: 'Why are projects run-of-the-river in the Himalaya?'
- Statement: 'Hydropower has no effect on the environment' - false, as slopes, forests and flow can all be affected.
- Odd one out: a hot spring or a lake placed among power projects.
Worked example 4. Question: 'Reshi, Teesta III, Dikchu, Rangit: which is not a hydroelectric project?' Working: Reshi is a hot spring on the Rangit. The other three are names linked with power projects or the river that carries one. Answer: Reshi.
Hydropower = steep fall + steady flow. Run-of-the-river = little storage. Weigh power against slopes, forests and flood risk. Check the present position of any project.
Key takeaways: A hydroelectric scheme turns the fall of a river into power through a dam, tunnel, penstock, turbine and generator. Sikkim's projects include Teesta III, Teesta V, Dikchu and Rangit. Good answers weigh clean power against landslide, forest and flood concerns.
Check your understanding
-
1. A run-of-the-river project:
- Uses the natural flow with little storage
- Needs a huge lake behind it
- Burns coal
- Works only in winter
Show answer
Answer: A. It diverts the flowing water through a tunnel and returns it downstream.
-
2. Which river is used by the Teesta III project?
- The Rangit
- The Rangpo Chu
- The Teesta
- The Brahmaputra
Show answer
Answer: C. Teesta III is on the upper Teesta near Chungthang.
-
3. What does the turbine do?
- Stores the water
- Cleans the water
- Spins and drives the generator
- Carries the power to homes
Show answer
Answer: C. Moving water spins the turbine and the generator turns that motion into electricity.
-
4. A concern about tunnels on Sikkim's slopes is:
- They may trigger landslides on young, loose slopes
- They make the slopes flat
- They create glaciers
- They dry up the sea
Show answer
Answer: A. Excavation on steep young slopes can destabilise them.
-
5. Which is NOT a use of water in Sikkim?
- Hydroelectric power
- Terrace irrigation
- Drinking water from springs
- Making salt from sea water
Show answer
Answer: D. Sikkim is landlocked in the mountains, so it has no sea water works.