Cutting with scissors, wheeling a barrow, lifting water from a well and loading a drum onto a truck all use simple machines. These questions combine ideas of moment, work and power. The method is to find the quantity that stays equal (moment about the pivot, or energy), then solve for the unknown. In this lesson take g = 10 m/s².
Rules
- Lever balance: effort × effort arm = load × load arm. Mechanical advantage MA = load ÷ effort = effort arm ÷ load arm.
- Classes: first class (pivot between effort and load, e.g. a crowbar, scissors); second class (load between pivot and effort, e.g. a wheelbarrow, nutcracker); third class (effort between pivot and load, e.g. tweezers, a fishing rod). A third-class lever has MA less than 1; it is useful for control and speed.
- Inclined plane (ideal, no friction): effort × length of ramp = load × height, so effort = load × height ÷ length.
- Work = force × distance; power = work ÷ time; efficiency = useful work ÷ work input.
Worked examples
Example 1 (crowbar). A crowbar is used to lift a 500 N stone. The effort arm is 1.5 m and the load arm is 0.3 m. Effort = 500 × 0.3 ÷ 1.5 = 100 N. MA = 500 ÷ 100 = 5.
Example 2 (wheelbarrow). The load of 400 N acts 0.5 m from the wheel axle (the pivot); the hands are 1.6 m from the axle. Effort = 400 × 0.5 ÷ 1.6 = 125 N. The effort arm is longer than the load arm, so MA = 3.2.
Example 3 (tweezers). The effort is applied 4 cm from the pivot and the tip holds a load 12 cm from the pivot. To hold a load of 2 N: effort = 2 × 12 ÷ 4 = 6 N. MA = 2 ÷ 6 = 1/3, less than 1, but the tip moves further than the fingers, giving fine control.
Example 4 (well). A person raises a 20 kg bucket from a well 10 m deep in 25 s. Work = mgh = 20 × 10 × 10 = 2000 J. Power = 2000 ÷ 25 = 80 W.
Example 5 (ramp). A 100 kg drum (weight 1000 N) is rolled up a 4 m ramp to a platform 1 m high. With no friction, effort = 1000 × 1 ÷ 4 = 250 N. With friction, suppose the effort needed is 312.5 N. Work input = 312.5 × 4 = 1250 J. Useful work = 1000 × 1 = 1000 J. Efficiency = 1000 ÷ 1250 = 0.8 = 80%. The ramp reduces the force but the work is never reduced.
Traps
- Using the total length of the lever instead of the distance from the pivot.
- Treating a machine as a source of energy. It only trades force for distance.
- Mixing up the load arm and the effort arm in second- and third-class levers.
- Using the weight in kg as force. Multiply by g to get newtons.
Effort × effort arm = load × load arm. Ramp: effort = load × height ÷ length. Power = work ÷ time. Efficiency = useful work ÷ input.
Key takeaways
- Balance the moments about the pivot.
- A long ramp or a long handle reduces the force needed, but not the work.
- Use efficiency to account for friction.
Check your understanding
-
1. A crowbar with an effort arm of 1.2 m and a load arm of 0.2 m is used to raise a load of 600 N. The effort needed is:
- 3600 N
- 200 N
- 720 N
- 100 N
Show answer
Answer: D. Effort = load × load arm ÷ effort arm = 600 × 0.2 ÷ 1.2 = 100 N.
-
2. A pair of tweezers is a lever of which class?
- Class I
- Class II
- Class III
- Class IV
Show answer
Answer: C. The effort is applied between the pivot (where the arms join) and the load at the tips: a third-class lever.
-
3. A boy of mass 40 kg climbs stairs through a vertical height of 5 m in 10 s (g = 10 m/s²). His power output is:
- 20 W
- 200 W
- 2000 W
- 400 W
Show answer
Answer: B. Work = 40 × 10 × 5 = 2000 J. Power = 2000 ÷ 10 = 200 W.
-
4. A frictionless ramp 3 m long rises 0.6 m. The effort needed to push a 500 N load up it is:
- 100 N
- 300 N
- 500 N
- 83 N
Show answer
Answer: A. Effort = load × height ÷ length = 500 × 0.6 ÷ 3 = 100 N.
-
5. A machine takes in 1250 J of work and gives out 1000 J of useful work. Its efficiency is:
- 125%
- 50%
- 75%
- 80%
Show answer
Answer: D. Efficiency = 1000 ÷ 1250 = 0.8 = 80%.