Analysing deviations: critical point control and management by exception

Explain how deviations are analysed using an acceptable range, critical point control and management by exception, state the advantages of these principles, and list the common causes of deviations.

If something looks wrong, please tell us.

By the end of this lesson you can

  • Explain the acceptable range of deviation and why significant deviations get priority.
  • Explain critical point control and management by exception, with their advantages.
  • Identify possible causes of deviations in a case.

Some deviation is expected in every activity. Managers therefore decide an acceptable range of deviation, and deviations in key areas are attended to more urgently than those in insignificant areas. Two principles help.

Critical point control

It is neither economical nor easy to check every activity. Control should focus on key result areas (KRAs) that are critical to the organisation's success; these are set as critical points. If anything goes wrong at a critical point, the whole organisation suffers. In a manufacturing firm, for example, a 5 per cent rise in labour cost may be more troublesome than a 15 per cent rise in postal charges.

Management by exception

Management by exception, also called control by exception, rests on the belief that trying to control everything results in controlling nothing. Only significant deviations beyond the permissible limit are brought to management's notice. If the plan allows a 2 per cent increase in labour cost, only increases beyond 2 per cent are reported; a major deviation, say 5 per cent, needs immediate priority action.

Critical point control and management by exception

  • Critical point control
    • Focuses on key result areas
    • Asks: which activities matter most?
    • Small changes at critical points get attention
  • Management by exception
    • Focuses on deviations beyond the permissible limit
    • Asks: which deviations are significant?
    • Routine deviations are left to subordinates
Advantages of critical point control and management by exception
AdvantageExplanation
Saves time and effortManagers deal only with significant deviations
Focuses attention on important areasBetter use of managerial talent
Facilitates delegationRoutine problems left to subordinates, which raises their morale
Identifies critical problemsProblems needing timely action are spotted early

Critical point control: watch the key result areas. Management by exception: report only deviations beyond the permissible limit. Trying to control everything ends in controlling nothing.

Finding the causes

After identifying significant deviations, managers must find their causes, because without the exact cause the right corrective action is not possible. According to the textbook, deviations may arise from unrealistic standards, defective processes, inadequate resources, structural drawbacks, organisational constraints and environmental factors beyond the organisation's control. The deviations and causes are then reported and corrective action is taken at the appropriate level.

Possible causes of deviations

  • Unrealistic standards
  • Defective process
  • Inadequacy of resources
  • Structural drawbacks
  • Organisational constraints
  • Environmental factors beyond control

Worked example 1: applying management by exception (illustrative)

A made-up firm allows a deviation of 2 per cent above budget in each cost. Budgets and actuals for a month:

Cost report of a made-up firm (illustrative, ₹)
Cost itemBudget (₹)Actual (₹)Deviation (₹)Deviation (%)Report to management?
Labour5,00,0005,25,00025,0005.0Yes, urgently
Power1,00,0001,01,5001,5001.5No
Stationery20,00020,3003001.5No
Raw material8,00,0008,24,00024,0003.0Yes

Working: labour 25,000 ÷ 5,00,000 × 100 = 5 per cent; power 1,500 ÷ 1,00,000 × 100 = 1.5 per cent; stationery 300 ÷ 20,000 × 100 = 1.5 per cent; raw material 24,000 ÷ 8,00,000 × 100 = 3 per cent. Only labour and raw material exceed the permissible 2 per cent, so only they are reported; labour, at 5 per cent and a key cost, needs priority action. Power and stationery are left to subordinates.

Worked example 2: critical points

A made-up hospital's managers ask which deviations they should watch most closely: (a) delay in emergency patients being seen; (b) late delivery of newspapers to the waiting room; (c) shortage of oxygen cylinders. Answer: (a) and (c) are critical points (key result areas), since failure there harms the whole organisation's purpose; (b) is minor.

Worked example 3: finding the cause

Case (made up): a made-up courier firm misses its delivery-time standard by 20 per cent. Investigation shows that half its vans are old and break down often. Cause: inadequacy of resources (defective, outdated vehicles). If instead the standard had been set without allowing for city traffic, the cause would be an unrealistic standard.

Key takeaways: managers fix an acceptable range of deviation and give priority to deviations in key areas. Critical point control focuses on key result areas; management by exception reports only significant deviations beyond the permissible limit. Together they save time, focus attention, help delegation and spot critical problems. Causes of deviations include unrealistic standards, defective processes, inadequate resources, structural drawbacks, organisational constraints and environmental factors.

Check your understanding

  1. 1. 'An attempt to control everything results in controlling nothing.' This belief underlies:

    1. critical point control
    2. management by exception
    3. sample checking
    4. budgetary control
    Show answer

    Answer: B. Management by exception holds that trying to control everything controls nothing, so only significant deviations beyond the permissible limit are brought to management's notice.

  2. 2. Focusing control on key result areas that are critical to the organisation's success is called:

    1. critical point control
    2. management by exception
    3. corrective action
    4. personal observation
    Show answer

    Answer: A. Critical point control focuses on key result areas (KRAs); if anything goes wrong at these points, the whole organisation suffers.

  3. 3. A made-up firm allows a 3 per cent deviation. Its budgeted transport cost is ₹2,00,000 and actual is ₹2,08,000. Should the deviation be reported under management by exception?

    1. No, because the deviation is 3 per cent exactly
    2. No, because the deviation is only ₹8,000
    3. Yes, because the deviation of 4 per cent exceeds the permissible 3 per cent
    4. Yes, because every deviation must be reported
    Show answer

    Answer: C. Deviation = 2,08,000 − 2,00,000 = ₹8,000; percentage = 8,000 ÷ 2,00,000 × 100 = 4 per cent, which is beyond the permissible 3 per cent, so it is reported.

  4. 4. Which of the following is an advantage of management by exception?

    1. Every small deviation reaches top management
    2. It removes the need for standards
    3. It stops delegation
    4. It saves managers' time and facilitates delegation of routine problems
    Show answer

    Answer: D. Managers deal only with significant deviations, saving time and effort, while routine problems are left to subordinates, which facilitates delegation and morale.

  5. 5. Assertion (A): It is necessary to identify the exact cause of a deviation. Reason (R): Without knowing the exact cause, appropriate corrective action may not be possible.

    1. A is true, but R is false
    2. A is false, but R is true
    3. Both A and R are true, and R is the correct explanation of A
    4. Both A and R are true, but R is not the correct explanation of A
    Show answer

    Answer: C. Both are true and R explains A: corrective action must address the cause, so the cause must be identified first.