Taking corrective action and the whole control process
Explain the final step of taking corrective action, match common causes of deviations with suitable remedies, and apply the full controlling process to a case.
If something looks wrong, please tell us.
By the end of this lesson you can
- Explain when corrective action is and is not needed, and when standards must be revised.
- Match common causes of deviations with suitable corrective actions.
- Apply all five steps of controlling to a business case.
Step 5: Taking corrective action
No corrective action is needed when deviations are within acceptable limits. When deviations go beyond the acceptable range, especially in important areas, they need immediate attention so that they do not recur and standards are achieved. Corrective action may mean training employees if a production target was not met, or assigning more workers and equipment and allowing overtime if an important project is behind schedule. If a deviation cannot be corrected through managerial action, the standards may have to be revised.
| Cause of deviation | Possible corrective action |
|---|---|
| Defective material | Change the quality specification for materials |
| Defective machinery | Repair the existing machinery or replace it |
| Obsolete machinery | Upgrade the technology |
| Defective process | Modify the existing process |
| Defective physical conditions of work | Improve the physical conditions of work |
| Ineffective training | Introduce new training programmes |
| Ineffective supervision | Change the supervisor or motivate supervisors |
| Absence of motivation | Introduce new incentive plans |
| Unrealistic standards | Revise the standards |
Corrective action: none if within limits; act on significant deviations by removing their cause; revise standards if the deviation cannot be corrected by managerial action.
The process as a whole
The five steps form a loop. The result of corrective action and any revised standards feed into the next period's plans, which is why controlling brings the management cycle back to planning.
The control loop
- Set standards From plans.
- Measure performance Objectively, in the same units.
- Compare Find the deviation.
- Analyse Significant deviations and their causes.
- Correct Remove causes or revise standards; feed into new plans.
Then back to step 1: Set standards
Techniques named in the textbook
The textbook's summary names traditional techniques of control (personal observation, statistical reports, breakeven analysis and budgetary control) and modern techniques (return on investment, ratio analysis, responsibility accounting, management audit, PERT and CPM, and management information systems). This course focuses on the meaning, importance, limitations and process of controlling explained in the chapter's text.
Worked example 1: the full process in a case (illustrative figures)
Case (made up): Fresh Fold, a made-up packaging company, plans to make 10,000 cartons a week with not more than 1 per cent defective, and allows a 2 per cent shortfall in output.
Step 1, standards: 10,000 cartons a week; defects at most 1 per cent, that is 10,000 × 1 ÷ 100 = 100 cartons. Step 2, measurement: actual output 9,400 cartons, 235 of them defective, measured through daily reports and sample checking. Step 3, comparison: output shortfall = 10,000 − 9,400 = 600 cartons = (600 ÷ 10,000) × 100 = 6 per cent; defects = (235 ÷ 9,400) × 100 = 2.5 per cent. Step 4, analysis: both deviations exceed the permissible limits, so they are significant. Investigation finds that one gluing machine is old and breaks down, and two new operators were not trained on it. Step 5, corrective action: repair or replace the machine (defective machinery) and run a training programme for the operators (ineffective training). Next week's results are measured again.
Worked example 2: no action needed
A made-up shop's sales standard is ₹5,00,000 for the month, with 3 per cent accepted variation. Actual sales are ₹4,90,000. Working: shortfall = 10,000; percentage = 10,000 ÷ 5,00,000 × 100 = 2 per cent, within 3 per cent. Decision: no corrective action is needed.
Worked example 3: revising the standard
Case (made up): a made-up delivery firm's standard of 30-minute delivery is missed every day by every rider, despite new bikes and training, because the city has closed a main road for two years. Reasoning: managerial action cannot correct a deviation caused by an outside factor of this kind, so the standard should be revised, for example to 40 minutes.
Key takeaways: corrective action is needed only for deviations beyond acceptable limits, especially in key areas. Remedies depend on causes: change material specifications, repair or replace machinery, upgrade technology, modify processes, improve conditions, train, change or motivate supervisors, introduce incentives, or revise unrealistic standards. The five steps form a loop that feeds back into planning.
Check your understanding
-
1. When is corrective action NOT required?
- When deviations are in key result areas
- When deviations exceed the permissible limit
- When deviations are within acceptable limits
- When a project is behind schedule
Show answer
Answer: C. No corrective action is required when deviations are within acceptable limits; action is needed when they go beyond the acceptable range, especially in important areas.
-
2. If a deviation is caused by obsolete machinery, the suitable corrective action is to:
- change the supervisor
- revise incentive plans
- improve canteen facilities
- upgrade the technology
Show answer
Answer: D. Obsolete machinery is corrected by upgrading technology; defective machinery may be repaired or replaced.
-
3. If a deviation cannot be corrected through managerial action, the manager should:
- revise the standards
- ignore the deviation forever
- stop measuring performance
- abolish planning
Show answer
Answer: A. When managerial action cannot correct a deviation, the standards may have to be revised so that they are realistic.
-
4. A made-up firm's standard output is 2,000 units with a 5 per cent permitted shortfall. Actual output is 1,880 units. Is corrective action needed?
- No, the shortfall is 5 per cent
- No, the shortfall is 120 units only
- Yes, the shortfall is 12 per cent
- Yes, the shortfall of 6 per cent exceeds the permitted 5 per cent
Show answer
Answer: D. Shortfall = 2,000 − 1,880 = 120 units; percentage = 120 ÷ 2,000 × 100 = 6 per cent, which is beyond the permitted 5 per cent, so corrective action is needed.
-
5. Assertion (A): Introducing new incentive plans is a suitable corrective action when deviations are due to lack of motivation. Reason (R): Corrective action should address the cause of the deviation.
- A is true, but R is false
- A is false, but R is true
- Both A and R are true, and R is the correct explanation of A
- Both A and R are true, but R is not the correct explanation of A
Show answer
Answer: C. Both are true and R explains A: if the cause is absence of motivation, the remedy that removes it is a new incentive plan.