EIA stages, questions and outputs
StageQuestion it answersMain output
ScreeningDoes the project need EIA, and at what level?Category or level of assessment
ScopingWhich issues and alternatives must be studied?Terms of reference
Baseline studyWhat is the environment like now?Baseline data across seasons
Impact prediction and evaluationWhat will change, and how significant is it?Ranked list of impacts
MitigationHow can harm be avoided, reduced, repaired or offset?Environmental management plan
Public consultationWhat do affected people and others say?Record of concerns and responses
Review and decisionIs the study adequate, and should the project proceed?Approval, approval with conditions, or rejection
Monitoring and auditIs the project performing as predicted and as required?Compliance reports, corrective action

Screening = whether; scoping = what; baseline = now; prediction = what will change; mitigation = what to do; consultation = who says what; decision = yes, yes with conditions, or no; monitoring = did it work.

Key takeaways: learn each stage with its question and output; the proponent prepares the report and the authority reviews and decides; monitoring closes the cycle; the screening–scoping swap and the baseline–monitoring swap are the classic traps; mistakes in screening and scoping are carried into every later stage.

Read the full lesson

Lesson 2

Impact identification methods: checklists, matrices, networks and overlays

Impact identification methods
MethodHow it worksStrengthWeakness
ChecklistA list of environmental factors to tick or describeSimple, quick, nothing major forgottenDoes not show cause and effect or indirect impacts
MatrixProject actions on one axis, environmental factors on the other; each cell marks an interactionLinks actions to factors; can score magnitude and importanceMostly direct impacts; scoring is subjective
NetworkChains of cause and effect drawn as a treeReveals indirect and higher-order impactsCan become large and complex
OverlayTransparent or digital map layers stacked over one anotherShows spatial patterns; good for route and site selectionPoor at non-spatial impacts such as social change

Checklist = completeness. Matrix = action × factor interactions. Network = cause-and-effect chains (indirect impacts). Overlay = maps (spatial patterns, siting). Weighted total = Σ (weight × score).

Key takeaways: match the method to the task: completeness suggests a checklist, interactions a matrix, indirect chains a network and spatial siting an overlay; the Leopold matrix scores magnitude and importance; weighted scoring helps compare alternatives but depends on the chosen weights, so the weights must be stated and tested.

Read the full lesson

Lesson 3

Predicting impacts with simple numbers: mixing, loads and standards

Load = concentration × flow. Mixed concentration = (Qr·Cr + Qe·Ce) ÷ (Qr + Qe). Design for the worst case, usually the lowest river flow.

Key takeaways: load equals concentration times flow; the mixed concentration is a flow-weighted average; required effluent quality comes from setting the mixed concentration equal to the standard and solving; low river flow is the critical case; these simple relations assume full mixing and no decay.

Read the full lesson

Lesson 4

Cumulative impacts and strategic environmental assessment

Cumulative impact = this project + other past, present and foreseeable activities. Remaining capacity = assimilative capacity − existing load. SEA = assessment of policies, plans and programmes, earlier and wider than project EIA.

Key takeaways: single-project EIA can miss slow cumulative decline; cumulative effects can add, interact or cross thresholds; assimilative capacity works like a budget; SEA assesses policies, plans and programmes, considers strategic alternatives and cumulative effects, and frames later project EIAs without replacing them.

Read the full lesson

Lesson 5

Mitigation plans, consultation, monitoring and the weak spots of EIA

Residual = initial × (1 − r1) × (1 − r2)… Removal efficiencies multiply, they do not add. EIA puts precaution, polluter pays and public participation into practice.

Key takeaways: judge the residual impact, not the gross one; sequential removal efficiencies multiply; the environmental management plan makes measures specific and monitorable; EIA is a practical tool for precaution, polluter pays and public participation; watch for conflict of interest, thin baselines, project splitting, token consultation and weak monitoring.

Read the full lesson

Lesson 6

Baseline surveys and indicators: what to measure and how to read the data

ComponentCommon indicatorsWhat a worrying value looks like
AirParticulate matter (PM10, PM2.5), sulphur dioxide, oxides of nitrogen, carbon monoxideValues above the legal limits
WaterpH, dissolved oxygen (DO), biochemical oxygen demand (BOD), turbidity, dissolved solids, coliform bacteriaLow DO, high BOD, high coliform count
NoiseEquivalent sound level in dB(A), day and nightLevels above limits for the zone
Land and soilLand use, erosion, soil fertility, contaminationBare, eroding or polluted soil
BiodiversitySpecies richness, presence of threatened species, habitat areaRare species or fragile habitat on the site
PeoplePopulation, livelihoods, income, health, literacy, land ownershipDependence on a resource the project will remove

Baseline = the condition before the project, measured across seasons with indicators matched to the expected impacts. Check individual readings, not only the mean.

  • Pick indicators for each component from the impacts you expect.
  • BOD and DO tell the story of organic pollution in water.
  • Cover seasons, and look beyond averages to exceedances.
Read the full lesson

Lesson 7

Noise problems: adding decibels and applying distance rules

Equal sources: +3 dB for two, +6 dB for four, +10 dB for ten. Point source: -6 dB per doubling of distance. Line source: -3 dB per doubling. Never add decibels arithmetically.

  • Decibels are logarithmic: convert to intensity, add, convert back, or use the shortcuts.
  • Distance rules depend on whether the source is a point or a line.
  • Finish by comparing the predicted level with the limit and deciding on mitigation.
Read the full lesson

Lesson 8

Public consultation, review and the decision: statement traps

Consult early, inform in plain language, answer comments, review independently, and decide: approve, approve with conditions, request more information or reject. EIA supports the decision; it does not make it.

Read the full lesson

Lesson 9

Cost-benefit and weighted-score problems: mixed numerical practice

NPV > 0 and BCR > 1 mean a project passes. Payback ignores discounting. Weighted scores depend on weights: test the ranking under more than one set.

  • Discount before comparing; undiscounted totals overstate gains.
  • Environmental losses can reverse a positive NPV.
  • Rankings by weighted score are sensitive to the weights.