Work done and work left
- Whole job: 12 days The job is treated as 1.
- One day: 1/12 1 divided by the days for the whole job.
- 5 days: 5/12 Days worked × one day's work.
- Left: 7/12 1 - 5/12.
If a job takes n days, one day's work is 1/n. Work done = days worked × one day's work.
- Treat the whole job as 1.
- One day's work is 1 divided by the days for the whole job.
- Remaining work = 1 - work done.