Two more exam patterns: workers who take turns day by day, and a worker who leaves a few days before the job ends. Both are easy with the LCM method.
Alternate days
Alternate days: a two-day cycle
- Day 1: A works A does 3 of the 30 units.
- Day 2: B works B does 2 units, so each cycle completes 5 units.
Then back to step 1: Day 1: A works
A takes 10 days and B takes 15 days. They work on alternate days, starting with A. Total work = 30 units; A does 3 units and B does 2 units. A two-day cycle completes 5 units. After 12 days (six cycles), 30 units are done, so the job finishes in 12 days. If the total were not a whole number of cycles, work out the last partial cycle day by day.
Leaving before the end
A leaves 5 days before the end
- Let the job last x days Total 60 units; A does 3 and B does 2 a day.
- Days each works B works x days; A works (x - 5) days.
- Equation 2x + 3(x - 5) = 60.
- x = 15 days 5x - 15 = 60.
A can do a job in 20 days and B in 30 days. They start together, but A leaves 5 days before the work is finished. How long does the job take? Total work 60 units; A = 3, B = 2 per day. Let the job last x days. B works all x days and A works (x - 5) days. So 2x + 3(x - 5) = 60, which gives 5x - 15 = 60, so x = 15 days.
Worked example 1
A can do a job in 12 days and B in 24 days. They start together and A leaves 3 days before completion. Total = 24 units; A = 2, B = 1 per day. With x days: x + 2(x - 3) = 24, so 3x = 30 and x = 10 days. Check: B 10 units + A (7 days × 2 = 14) = 24.
Worked example 2: worker does some days alone
A can do a job in 10 days and works alone for 4 days. B can do it in 15 days and finishes the rest. A completes 4/10 = 2/5. The rest is 3/5, which takes B 15 × 3/5 = 9 days.
Write the days each person works, multiply by their daily units, and set the total equal to the whole work.
Key takeaways
- Alternate-day problems repeat a two-day cycle.
- For a worker who leaves early, give them fewer days in the equation.
- Check by adding the units each person did.
Check your understanding
-
1. A takes 6 days and B takes 12 days to do a job. They work on alternate days, starting with A. In how many days is the job finished?
- 6
- 8
- 9
- 10
Show answer
Answer: B. Total = 12 units; A = 2, B = 1. Each two-day cycle does 3 units. Four cycles (8 days) do 12 units, so the job ends after 8 days.
-
2. A takes 4 days and B takes 6 days to do a job. They work on alternate days, starting with A. On which day is the job completed?
- Day 3
- Day 4
- Day 5
- Day 6
Show answer
Answer: C. Total = LCM(4, 6) = 12 units; A = 3, B = 2. Two full cycles (4 days) do 10 units, leaving 2. Day 5 is A's day, and A does up to 3 units, so the job is completed during day 5 (after 4⅔ days).
-
3. A takes 10 days and B takes 15 days. They start together, but A leaves 5 days before the job is finished. How long does the whole job take?
- 7 days
- 8 days
- 8.5 days
- 9 days
Show answer
Answer: D. Total = 30 units; A = 3, B = 2 a day. If the job takes x days, B works x days and A works (x − 5) days: 2x + 3(x − 5) = 30, so 5x = 45 and x = 9. Check: B 18 units + A 4 days × 3 = 12 units = 30.
-
4. A can do a job in 12 days and works alone for 3 days. B, who can do the whole job in 16 days, finishes the rest. How many days does B work?
- 12
- 13
- 14
- 16
Show answer
Answer: A. A does 3/12 = 1/4 of the job, leaving 3/4. B needs 3/4 × 16 = 12 days.
-
5. A and B together can do a job in 10 days. After 4 days A leaves, and B finishes the rest in 9 more days. How long would B take alone?
- 12 days
- 15 days
- 18 days
- 20 days
Show answer
Answer: B. In 4 days together they do 4/10 = 2/5, leaving 3/5. B does 3/5 in 9 days, so the whole job takes B 9 × 5/3 = 15 days.