Working together
Add individual work rates to find the time taken together, and subtract to find one person's time.
If something looks wrong, please tell us.
When people work together, their one-day rates add up. This single idea solves most time and work questions.
Adding rates
If A takes a days and B takes b days, together in one day they do 1/a + 1/b of the job. The time taken together is 1 ÷ (1/a + 1/b) = ab ÷ (a + b).
Worked example 1
Rates add when working together
- One-day rates A does 1/10 and B does 1/15 each day.
- Add the rates 3/30 + 2/30 = 5/30 = 1/6 of the job a day.
- Together: 6 days Check: (10 × 15) ÷ 25 = 6.
A can do a job in 10 days and B in 15 days. Together, one day's work = 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6. So they finish in 6 days. Formula check: (10 × 15) ÷ 25 = 150 ÷ 25 = 6.
Worked example 2: finding one person's time
A and B together can do a job in 12 days. A alone takes 20 days. Find B's time. One day: A + B = 1/12, A = 1/20. So B = 1/12 - 1/20 = 5/60 - 3/60 = 2/60 = 1/30. B alone takes 30 days.
| A alone | B alone | Together |
|---|---|---|
| 10 days | 15 days | 6 days |
| 12 days | 6 days | 4 days |
| 20 days | 30 days | 12 days |
| 8 days | 8 days | 4 days |
Together time = ab ÷ (a + b) for two workers. Rates add; times do not.
Key takeaways
- Add one-day rates for people working together.
- Subtract a known rate from the combined rate to get the other.
- Together time is always shorter than the quicker worker's alone time.
Check your understanding
-
1. A can do a job in 12 days and B in 24 days. Working together, how long do they take?
- 6 days
- 8 days
- 9 days
- 18 days
Show answer
Answer: B. One day together = 1/12 + 1/24 = 2/24 + 1/24 = 3/24 = 1/8, so 8 days. Formula: 12 × 24 ÷ 36 = 8.
-
2. A and B together finish a job in 10 days. A alone takes 15 days. How long does B take alone?
- 5 days
- 20 days
- 25 days
- 30 days
Show answer
Answer: D. B's rate = 1/10 − 1/15 = 3/30 − 2/30 = 1/30, so B takes 30 days. (Subtracting the days, 15 − 10 = 5, is the classic trap: rates subtract, times do not.)
-
3. Three workers each take 9 days to do a job alone. How long do they take working together?
- 3 days
- 4.5 days
- 9 days
- 27 days
Show answer
Answer: A. Together one day = 1/9 + 1/9 + 1/9 = 3/9 = 1/3, so 3 days.
-
4. A can do a job in 15 days and B in 10 days. Working together, how long do they take?
- 4 days
- 5 days
- 6 days
- 12.5 days
Show answer
Answer: C. 1/15 + 1/10 = 2/30 + 3/30 = 5/30 = 1/6, so 6 days. Formula: 15 × 10 ÷ 25 = 6.
-
5. A and B together finish a job in 4 days; A alone takes 6 days. What part of the job does B do in one day?
- 1/24
- 1/12
- 1/10
- 1/2
Show answer
Answer: B. B's one-day work = 1/4 − 1/6 = 3/12 − 2/12 = 1/12 (so B alone would take 12 days).