Work done in a day: the basic idea
Express a job as 1 whole and find the fraction of work done per day, the work done in several days, and the work left.
If something looks wrong, please tell us.
Time and work problems all follow one idea: a job is treated as 1 whole, and a worker's speed is the fraction of the job done each day. If you can handle fractions, you can do this chapter.
One day's work
If a person completes a job in n days, then one day's work = 1/n of the job. A worker who takes 10 days does 1/10 each day. In d days the work done = d/n, and the work left = 1 - d/n.
Worked example 1
Work done and work left
- Whole job: 12 days The job is treated as 1.
- One day: 1/12 1 divided by the days for the whole job.
- 5 days: 5/12 Days worked × one day's work.
- Left: 7/12 1 - 5/12.
A can complete a job in 12 days. What part is done in 5 days, and what part is left? One day = 1/12. In 5 days: 5/12. Left: 1 - 5/12 = 7/12.
Worked example 2: finding the days
A does 1/8 of a job per day. In how many days will 3/4 of the job be done? Days = (3/4) ÷ (1/8) = 3/4 × 8 = 6 days.
The formula in words
- Rate per day = 1 ÷ (days taken for the whole job).
- Work done = rate × days.
- Days needed = work to be done ÷ rate.
If a job takes n days, one day's work is 1/n. Work done = days worked × one day's work.
Key takeaways
- Treat the whole job as 1.
- One day's work is 1 divided by the days for the whole job.
- Remaining work = 1 - work done.
Check your understanding
-
1. A can complete a job in 20 days. What part of the job does he do in 8 days?
- 1/4
- 2/5
- 3/5
- 8/12
Show answer
Answer: B. One day's work = 1/20. In 8 days: 8 × 1/20 = 8/20 = 2/5.
-
2. A does 1/12 of a job each day. In how many days will he finish 2/3 of the job?
- 4
- 6
- 8
- 18
Show answer
Answer: C. Days = work to be done ÷ rate = (2/3) ÷ (1/12) = 2/3 × 12 = 8 days.
-
3. A can finish a job in 16 days. After working for 6 days, what part of the job is left?
- 3/8
- 1/2
- 3/5
- 5/8
Show answer
Answer: D. Work done = 6/16 = 3/8. Work left = 1 − 3/8 = 5/8.
-
4. A finishes 3/7 of a job in 6 days. How many days would he take for the whole job?
- 14
- 15
- 18
- 21
Show answer
Answer: A. Rate = (3/7) ÷ 6 = 3/42 = 1/14 of the job per day, so the whole job takes 14 days.
-
5. A can do a job in 25 days. He works for 10 days. How many more days does he need to finish?
- 10
- 15
- 20
- 25
Show answer
Answer: B. Work done = 10/25 = 2/5, so 3/5 is left. Days = (3/5) ÷ (1/25) = 15 days.