The LCM method

  1. Total work = LCM LCM(12, 18) = 36 units.
  2. Daily work A: 36 ÷ 12 = 3 units; B: 36 ÷ 18 = 2 units.
  3. Add for the team 3 + 2 = 5 units a day.
  4. Days 36 ÷ 5 = 7.2 days.
  1. Take total work = LCM of all the days.
  2. Daily work of a person = total work ÷ days taken.
  3. Add the daily works of those working together.
  4. Days = total work ÷ combined daily work.

Worked example 1

A can do a job in 12 days and B in 18 days. Total work = LCM(12, 18) = 36 units. A does 3 units a day; B does 2 units a day. Together 5 units a day. Time = 36 ÷ 5 = 7.2 days.

Worked example 2: three workers

A, B and C can finish a job in 10, 15 and 30 days. Total work = LCM = 30 units. A = 3, B = 2, C = 1 unit a day. Together = 6 units a day. Time = 30 ÷ 6 = 5 days.

Partial teamwork

A takes 20 days and B takes 30 days. They work together for 6 days, then A leaves. Total work 60 units; A = 3, B = 2. In 6 days they do 6 × 5 = 30 units. Remaining 30 units are done by B at 2 per day, taking 15 more days.

Total work = LCM of the days. Daily work = total ÷ days. Add daily works for a team.

— Method

Key takeaways

  • Choose total work = LCM to avoid fractions.
  • Daily work is a whole number of units.
  • For partial work, subtract units done from the total.

Check your understanding

  1. 1. A, B and C can finish a job in 20, 30 and 60 days. Working together, how long do they take?

    1. 8 days
    2. 10 days
    3. 12 days
    4. 15 days
    Show answer

    Answer: B. Total work = LCM(20, 30, 60) = 60 units. Daily work: A = 3, B = 2, C = 1, together 6 units. Time = 60 ÷ 6 = 10 days.

  2. 2. A can do a job in 8 days and B in 12 days. Working together, how long do they take?

    1. 4 days
    2. 4.5 days
    3. 4.8 days
    4. 5 days
    Show answer

    Answer: C. Total work = LCM(8, 12) = 24 units. A = 3, B = 2 units a day, together 5. Time = 24 ÷ 5 = 4.8 days.

  3. 3. A takes 12 days and B takes 18 days to do a job. They work together for 3 days, then B leaves. How many more days does A need?

    1. 4
    2. 5
    3. 6
    4. 7
    Show answer

    Answer: D. Total = LCM(12, 18) = 36 units; A = 3, B = 2 a day. In 3 days together: 3 × 5 = 15 units. Left: 21 units, which A does at 3 a day in 7 days.

  4. 4. A takes 15 days and B takes 25 days to do a job. Taking the total work as their LCM, how many units does each do in a day?

    1. A 5, B 3
    2. A 3, B 5
    3. A 15, B 25
    4. A 25, B 15
    Show answer

    Answer: A. Total work = LCM(15, 25) = 75 units. A does 75 ÷ 15 = 5 units a day and B does 75 ÷ 25 = 3. The faster worker does more units.

  5. 5. A takes 10 days and B takes 15 days. They work together for 4 days. What fraction of the job is left?

    1. 1/6
    2. 1/3
    3. 1/2
    4. 2/3
    Show answer

    Answer: B. Total = LCM(10, 15) = 30 units; A = 3, B = 2, together 5 a day. In 4 days they do 20 units, leaving 10 of 30 = 1/3.