Some workers are quicker than others. We call this their efficiency: how much work they get done in the same time. Efficiency and time are linked in a simple way: the faster the worker, the fewer days needed. This lesson shows the link and uses it in small, friendly problems.
The basic idea
Suppose A is twice as efficient as B. In any one day A does twice as much as B. So A needs only half of the time B needs. If B takes 30 days, A takes 15 days. In general, if the efficiencies are in the ratio 2 : 1, the times are in the ratio 1 : 2. The ratio of times is the reverse of the ratio of efficiencies.
| Efficiency of A : B | Time of A : B | If B takes 30 days, A takes |
|---|---|---|
| 2 : 1 | 1 : 2 | 15 days |
| 3 : 2 | 2 : 3 | 20 days |
| 5 : 4 | 4 : 5 | 24 days |
| 1 : 1 | 1 : 1 | 30 days |
Look at the second row: if A is 3 parts to B's 2 parts in efficiency, then A needs 2 parts of time where B needs 3 parts. Dividing 30 days into 3 parts gives 10 days a part, so A takes 2 × 10 = 20 days.
Worked example 1
A is twice as efficient as B, and B can finish a job in 30 days. How long does A take? A takes half the time of B, so 15 days. Check by days: in one day A does 1/15 and B does 1/30, so A does twice as much.
Worked example 2
Efficiency 3 : 2 to time
- Efficiency A : B = 3 : 2 A gets more done each day.
- Time A : B = 2 : 3 The reverse ratio.
- One part = 10 days A's 2 parts are 20 days.
- B takes 30 days B's 3 parts.
A and B work at efficiencies in the ratio 3 : 2. A alone can finish a job in 20 days. How long does B take? Times are in the reverse ratio, 2 : 3 for A : B. A's 2 parts equal 20 days, so one part is 10 days and B's 3 parts are 30 days. B takes 30 days.
Worked example 3: finding both times
A is twice as efficient as B. Working together, they finish a job in 10 days. Each day, A does 2 parts and B does 1 part, so together they do 3 parts a day. The whole job is 3 × 10 = 30 parts. B alone does 1 part a day, so B needs 30 days. A alone does 2 parts a day, so A needs 15 days. Check: 1/15 + 1/30 = 2/30 + 1/30 = 3/30 = 1/10.
Worked example 4: percentages
A is 25% more efficient than B. B can finish a job in 20 days. How long will A take? If B's efficiency is 4 parts, then A's is 4 + 25% of 4 = 5 parts. The efficiency ratio A : B is 5 : 4, so the time ratio is 4 : 5. B's 5 parts equal 20 days, so one part is 4 days and A takes 4 × 4 = 16 days. Check: A's rate is 1/16 and B's is 1/20, and 1/16 ÷ 1/20 = 20/16 = 1.25, which is 25% more.
Efficiency and time are in inverse ratio. If A is twice as fast, A takes half the time.
Turning times into efficiency
You can also go the other way. If A takes 6 days and B takes 9 days, the ratio of times is 6 : 9 = 2 : 3. The efficiencies are in the reverse ratio 3 : 2. So A is 1.5 times as efficient as B. A neat way to find efficiencies is to take a common total, such as the LCM of the times, and divide: with a total of 18 units, A does 3 units a day and B does 2 units a day.
Common slips
- Keeping the ratio the same way round. A faster worker has the smaller time, so the numbers swap.
- Saying that 'twice as efficient' means two days less. It means half the time, not two fewer days.
- With percentages, not choosing a base. Let the slower worker be 100 or a convenient number of parts.
Key takeaways
- Efficiency ratio and time ratio are reverses of each other.
- Turn a ratio into parts, and use the one known value to find the size of a part.
- For 'together' questions, add the parts per day and multiply by the days to find the whole job.
- A percentage more efficiency means more parts, not less time by the same percentage.
Check your understanding
-
1. A is twice as efficient as B. B takes 30 days. How long does A take?
- 15 days
- 20 days
- 25 days
- 60 days
Show answer
Answer: A. A is twice as fast, so A takes half of 30 days: 15 days.
-
2. The efficiency of A : B is 3 : 2, and A takes 20 days. How long does B take?
- 15 days
- 24 days
- 40 days
- 30 days
Show answer
Answer: D. Time ratio A : B is 2 : 3. Two parts are 20 days, so one part is 10 days and B takes 3 × 10 = 30 days.
-
3. A is twice as efficient as B. Together they finish a job in 10 days. How long does B take alone?
- 20 days
- 30 days
- 15 days
- 25 days
Show answer
Answer: B. A does 2 parts and B does 1 part a day, so the job is 3 × 10 = 30 parts. B does 1 part a day, so B takes 30 days.
-
4. A is 25% more efficient than B, and B takes 20 days. How long does A take?
- 15 days
- 18 days
- 25 days
- 16 days
Show answer
Answer: D. Efficiency A : B is 5 : 4, so the time ratio is 4 : 5. B's 5 parts are 20 days, so A's 4 parts are 16 days.
-
5. A takes 6 days and B takes 9 days for a job. What is the ratio of efficiency A : B?
- 2 : 3
- 3 : 2
- 6 : 9
- 1 : 3
Show answer
Answer: B. The time ratio 6 : 9 = 2 : 3 is reversed for efficiency, so A : B = 3 : 2.