Man-days, wages and pipes
Use the man-days idea, divide wages in proportion to work, and solve pipe-and-cistern problems.
If something looks wrong, please tell us.
Three extensions of the same ideas: counting work in man-days, dividing payment fairly, and filling or emptying tanks.
Three extensions of the same ideas
-
Man-days
- Men × days is constant for a job
- 10 men × 12 days = 120 man-days; 15 men take 8 days
-
Wages
- Shared in proportion to the work done
- Daily work 1/6 and 1/3 (1 : 2): ₹ 900 splits ₹ 300 and ₹ 600
-
Pipes and cisterns
- An inlet works like a worker; an outlet or leak is a negative worker
- 1/12 - 1/20 = 1/30, so the tank fills in 30 hours
Man-days
A job needing 10 men for 12 days is 10 × 12 = 120 man-days. With 15 men the time is 120 ÷ 15 = 8 days. More workers means fewer days: the product stays constant.
Worked example 1
20 men can complete a job in 15 days. After 5 days, 10 men leave. How many more days are needed? Total = 20 × 15 = 300 man-days. Done in 5 days = 100. Left = 200 man-days with 10 men, so 200 ÷ 10 = 20 more days.
Wages
Share payment in proportion to the work done. A takes 6 days and B takes 3 days alone. Working together for the same number of days, A's daily work is 1/6 and B's is 1/3, a ratio of 1 : 2. If the total wage is ₹ 900, A gets ₹ 300 and B gets ₹ 600.
Pipes and cisterns
An inlet pipe works like a worker and an outlet or leak like a negative worker. Pipe A fills a tank in 12 hours and a leak empties it in 20 hours. Together, net rate = 1/12 - 1/20 = 5/60 - 3/60 = 2/60 = 1/30, so the tank fills in 30 hours.
Man-days = men × days (constant for a job). Wages in the ratio of work done. Outlets subtract.
Key takeaways
- Men × days is constant for the same job.
- Wages follow the amount of work done, not just the days.
- Outlet pipes and leaks have negative rates.
Check your understanding
-
1. 18 men can finish a job in 20 days. How many days will 24 men take?
- 12
- 15
- 16
- 27
Show answer
Answer: B. Total work = 18 × 20 = 360 man-days. With 24 men: 360 ÷ 24 = 15 days. More men, fewer days.
-
2. 15 men can finish a job in 24 days. After 8 days, 5 more men join. How many more days are needed?
- 8
- 10
- 12
- 16
Show answer
Answer: C. Total = 15 × 24 = 360 man-days. In 8 days: 15 × 8 = 120 done, 240 left. Now 20 men: 240 ÷ 20 = 12 more days.
-
3. A alone can do a job in 10 days and B alone in 15 days. Working together they finish it and are paid ₹1,500. What is A's fair share?
- ₹600
- ₹750
- ₹800
- ₹900
Show answer
Answer: D. Share in the ratio of work done. Daily work 1/10 : 1/15 = 3 : 2. A gets 3/5 of 1,500 = ₹900 and B gets ₹600.
-
4. Pipe A fills a tank in 10 hours and pipe B empties a full tank in 15 hours. If both are open, how long does the empty tank take to fill?
- 30 hours
- 25 hours
- 12 hours
- 6 hours
Show answer
Answer: A. The outlet works like a negative worker: net rate = 1/10 − 1/15 = 3/30 − 2/30 = 1/30, so 30 hours. (6 hours wrongly adds the two rates.)
-
5. Pipe A fills a tank in 4 hours and pipe B in 12 hours. With both open, how long does the tank take to fill?
- 2 hours
- 3 hours
- 6 hours
- 8 hours
Show answer
Answer: B. 1/4 + 1/12 = 3/12 + 1/12 = 4/12 = 1/3, so 3 hours.