Man-days, wages and pipes

Use the man-days idea, divide wages in proportion to work, and solve pipe-and-cistern problems.

If something looks wrong, please tell us.

Three extensions of the same ideas: counting work in man-days, dividing payment fairly, and filling or emptying tanks.

Three extensions of the same ideas

  • Man-days
    • Men × days is constant for a job
    • 10 men × 12 days = 120 man-days; 15 men take 8 days
  • Wages
    • Shared in proportion to the work done
    • Daily work 1/6 and 1/3 (1 : 2): ₹ 900 splits ₹ 300 and ₹ 600
  • Pipes and cisterns
    • An inlet works like a worker; an outlet or leak is a negative worker
    • 1/12 - 1/20 = 1/30, so the tank fills in 30 hours

Man-days

A job needing 10 men for 12 days is 10 × 12 = 120 man-days. With 15 men the time is 120 ÷ 15 = 8 days. More workers means fewer days: the product stays constant.

Worked example 1

20 men can complete a job in 15 days. After 5 days, 10 men leave. How many more days are needed? Total = 20 × 15 = 300 man-days. Done in 5 days = 100. Left = 200 man-days with 10 men, so 200 ÷ 10 = 20 more days.

Wages

Share payment in proportion to the work done. A takes 6 days and B takes 3 days alone. Working together for the same number of days, A's daily work is 1/6 and B's is 1/3, a ratio of 1 : 2. If the total wage is ₹ 900, A gets ₹ 300 and B gets ₹ 600.

Pipes and cisterns

An inlet pipe works like a worker and an outlet or leak like a negative worker. Pipe A fills a tank in 12 hours and a leak empties it in 20 hours. Together, net rate = 1/12 - 1/20 = 5/60 - 3/60 = 2/60 = 1/30, so the tank fills in 30 hours.

Man-days = men × days (constant for a job). Wages in the ratio of work done. Outlets subtract.

— Rules

Key takeaways

  • Men × days is constant for the same job.
  • Wages follow the amount of work done, not just the days.
  • Outlet pipes and leaks have negative rates.

Check your understanding

  1. 1. 18 men can finish a job in 20 days. How many days will 24 men take?

    1. 12
    2. 15
    3. 16
    4. 27
    Show answer

    Answer: B. Total work = 18 × 20 = 360 man-days. With 24 men: 360 ÷ 24 = 15 days. More men, fewer days.

  2. 2. 15 men can finish a job in 24 days. After 8 days, 5 more men join. How many more days are needed?

    1. 8
    2. 10
    3. 12
    4. 16
    Show answer

    Answer: C. Total = 15 × 24 = 360 man-days. In 8 days: 15 × 8 = 120 done, 240 left. Now 20 men: 240 ÷ 20 = 12 more days.

  3. 3. A alone can do a job in 10 days and B alone in 15 days. Working together they finish it and are paid ₹1,500. What is A's fair share?

    1. ₹600
    2. ₹750
    3. ₹800
    4. ₹900
    Show answer

    Answer: D. Share in the ratio of work done. Daily work 1/10 : 1/15 = 3 : 2. A gets 3/5 of 1,500 = ₹900 and B gets ₹600.

  4. 4. Pipe A fills a tank in 10 hours and pipe B empties a full tank in 15 hours. If both are open, how long does the empty tank take to fill?

    1. 30 hours
    2. 25 hours
    3. 12 hours
    4. 6 hours
    Show answer

    Answer: A. The outlet works like a negative worker: net rate = 1/10 − 1/15 = 3/30 − 2/30 = 1/30, so 30 hours. (6 hours wrongly adds the two rates.)

  5. 5. Pipe A fills a tank in 4 hours and pipe B in 12 hours. With both open, how long does the tank take to fill?

    1. 2 hours
    2. 3 hours
    3. 6 hours
    4. 8 hours
    Show answer

    Answer: B. 1/4 + 1/12 = 3/12 + 1/12 = 4/12 = 1/3, so 3 hours.