Practice questions often express speed as a percentage: 'A is 20% more efficient than B' or 'the workers become 25% faster'. The trap is that time does not change by the same percentage as efficiency. This lesson gives a reliable way to convert percentages into ratios, and then into time, and shows how to deal with jobs where the speed changes part-way.

From percentage to ratio

Take the slower or original efficiency as 100 parts. If A is 20% more efficient than B, then when B is 100, A is 120, a ratio of 6 : 5. The time ratio is the reverse, 5 : 6. So if B takes 24 days, A takes 24 × 5/6 = 20 days. If A is only 60% as efficient as B, then A : B = 60 : 100 = 3 : 5, and the time ratio is 5 : 3, so A takes 5/3 times as long as B.

A table to remember

Efficiency changes byNew time isTime changes by
+25%4/5 of old time20% less
+50%2/3 of old time33 1/3% less
+100%1/2 of old time50% less
−20%5/4 of old time25% more
−50%2 times old time100% more

Each row follows from the same rule: new time = old time ÷ (new efficiency ÷ old efficiency). For +25%, the new efficiency is 125 and the old is 100, so the new time is 100/125 = 4/5 of the old time.

Worked example 1

A is 20% more efficient than B. B takes 24 days. How long does A take? A : B efficiency is 120 : 100 = 6 : 5, so the time ratio is 5 : 6. B's 6 parts equal 24 days, so one part is 4 days, and A takes 5 × 4 = 20 days.

Worked example 2

A is 60% as efficient as B. B can finish a job in 15 days. How long does A take? A : B = 3 : 5, so the time ratio is 5 : 3. B's 3 parts equal 15 days, so one part is 5 days, and A takes 5 × 5 = 25 days.

Worked example 3: a job takes less time

A job takes a worker 40 days. After training her efficiency increases by 25%. How many days does she now need, and how many does she save? The new time is 4/5 of 40 = 32 days. She saves 8 days, which is 20% of the old time.

Worked example 4: speed changes part-way

A worker normally finishes a job in 40 days. For the first 10 days he works at only 80% of his normal efficiency, and after that at full efficiency. How long does the whole job take? In the first 10 days he does the work of 80% of 10 = 8 normal days. The remaining work is 40 − 8 = 32 normal days, done at full speed in 32 days. The total is 10 + 32 = 42 days, so he is 2 days late.

Efficiency up by x% does not cut time by x%. Convert to a ratio, reverse it for time, then apply it to the known time.

— Rule to remember

Worked example 5: a team

A team of workers finishes a job in 30 days. If their efficiency falls by 20%, how long will the same job take? New efficiency is 80% of the old, so the new time is 30 ÷ 0.8 = 37.5 days, which is 25% more. Check with ratios: efficiency 4 : 5 means time 5 : 4, so 30 × 5/4 = 37.5.

Common slips

  • Thinking that 25% more efficiency means 25% less time. It means 20% less time.
  • Using the wrong base. Always take the person or machine you are compared with as 100.
  • Forgetting to reverse the ratio when moving from efficiency to time.
  • In part-way changes, treating the slow days as normal days. Convert the slow days to normal-day equivalents first.

Key takeaways

  • Efficiency ratio and time ratio are reverses.
  • x% more efficiency gives time of 100/(100 + x) of the old time.
  • Convert slow or fast stretches into normal-day equivalents.
  • Always check the answer by comparing the two rates directly.

Check your understanding

  1. 1. A is 20% more efficient than B. B takes 24 days. How long does A take?

    1. 20 days
    2. 18 days
    3. 19.2 days
    4. 28.8 days
    Show answer

    Answer: A. Efficiency A : B = 6 : 5, so time A : B = 5 : 6. Time for A = 24 × 5/6 = 20 days.

  2. 2. If a worker's efficiency increases by 25%, by what percentage does the time for the same job decrease?

    1. 25%
    2. 30%
    3. 15%
    4. 20%
    Show answer

    Answer: D. New time = 100/125 = 80% of the old time, so it decreases by 20%.

  3. 3. If a worker's efficiency falls by 20%, by what percentage does the time for the same job increase?

    1. 20%
    2. 25%
    3. 15%
    4. 30%
    Show answer

    Answer: B. New time = 100/80 = 125% of the old time, an increase of 25%.

  4. 4. A is 60% as efficient as B, and B takes 15 days. How long does A take?

    1. 9 days
    2. 20 days
    3. 30 days
    4. 25 days
    Show answer

    Answer: D. A : B = 3 : 5 in efficiency, so the time ratio is 5 : 3. A takes 15 × 5/3 = 25 days.

  5. 5. A worker normally needs 40 days. For the first 10 days he works at 80% efficiency, then at full efficiency. How many days in all?

    1. 40 days
    2. 42 days
    3. 45 days
    4. 50 days
    Show answer

    Answer: B. 10 days at 80% equal 8 normal days. 32 normal days remain, so the total is 10 + 32 = 42 days.