Work done in one day
Use the idea of 'part of the work per day' to combine workers and find missing times.
If something looks wrong, please tell us.
In Time and Work, the whole job counts as 1. If someone finishes a job in n days, they do 1/n of it each day. Add the daily parts when people work together.
Working together
If A takes a days and B takes b days, together they do 1/a + 1/b per day, and take 1 ÷ (1/a + 1/b) = ab ÷ (a + b) days.
Worked example 1
Question: A finishes a job in 12 days and B in 18 days. Together? Working: 1/12 + 1/18 = 3/36 + 2/36 = 5/36 per day. Time = 36/5 = 7.2 days. Answer: 7.2 days.
Worked example 2: finding one worker
Question: A and B together take 10 days. A alone takes 15 days. B alone? Working: B's daily work = 1/10 − 1/15 = 3/30 − 2/30 = 1/30. B takes 30 days. Answer: 30 days.
Worked example 3: part done, part left
Question: A can do a job in 20 days. He works for 5 days and leaves. B finishes the rest in 9 days. How long would B alone take? Working: A did 5/20 = 1/4. Left: 3/4. B does 3/4 in 9 days, so the whole job takes 9 ÷ 3/4 = 12 days. Answer: 12 days.
If someone takes n days, one day's work is 1/n. Together: add the daily parts. Remaining work = 1 − work done.
Key takeaways: think in daily work; add rates for people working together; and subtract for 'one leaves' problems.
Check your understanding
-
1. A can finish a job in 10 days and B in 15 days. Working together, how long do they take?
- 5 days
- 6 days
- 12.5 days
- 25 days
Show answer
Answer: B. A does 1/10 and B does 1/15 per day. Together 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6 per day, so the job takes 6 days. Adding the days (25) or averaging them (12.5) is the common trap.
-
2. A and B together finish a job in 8 days. A alone takes 12 days. How long does B alone take?
- 4 days
- 20 days
- 24 days
- 16 days
Show answer
Answer: C. B's daily work = together - A = 1/8 - 1/12 = 3/24 - 2/24 = 1/24. So B alone takes 24 days.
-
3. A can do a job in 18 days. After working for 4 days, what fraction of the job is still left?
- 7/9
- 2/9
- 5/9
- 4/9
Show answer
Answer: A. In 4 days A does 4/18 = 2/9 of the job. Work left = 1 - 2/9 = 7/9.
-
4. A can finish a job in 16 days. He works for 4 days and leaves, and B finishes the rest in 15 days. How long would B alone take for the whole job?
- 12 days
- 15 days
- 18 days
- 20 days
Show answer
Answer: D. A did 4/16 = 1/4, so 3/4 was left. B does 3/4 in 15 days, so the whole job takes 15 ÷ 3/4 = 20 days.
-
5. A can finish a job in 20 days and B in 30 days. They work together for 6 days. What fraction of the job is left?
- 1/3
- 1/2
- 2/3
- 1/4
Show answer
Answer: B. Together they do 1/20 + 1/30 = 3/60 + 2/60 = 5/60 = 1/12 per day. In 6 days: 6/12 = 1/2. Left = 1 - 1/2 = 1/2.