- Practice
- 15 practice questions
Final self-assessment: Time and Work
Test yourself on the whole course: 15 questions with answers explained.
If something looks wrong, please tell us.
Attempt all 15 questions without looking back at the lessons, then check your answers and read each explanation. The questions are a little harder than the checks after each lesson.
Final self-assessment
-
1. A can do a job in 12 days and B in 24 days. They work together for 4 days, then A leaves. How long does B take to finish the rest?
- 8 days
- 10 days
- 12 days
- 16 days
Show answer
Answer: C. Together: 1/12 + 1/24 = 3/24 = 1/8 per day, so in 4 days they do 1/2. B does the other 1/2 at 1/24 per day: 1/2 × 24 = 12 days.
-
2. A and B together finish a job in 6 days; A alone takes 10 days. How long does B alone take?
- 4 days
- 15 days
- 16 days
- 12 days
Show answer
Answer: B. B = 1/6 - 1/10 = 5/30 - 3/30 = 2/30 = 1/15. B alone takes 15 days.
-
3. A does 1/3 of a job in 5 days and B does 2/5 of it in 8 days. How long will they take to do the whole job together?
- 8 4/7 days
- 9 days
- 7 1/2 days
- 17 1/2 days
Show answer
Answer: A. A's whole job: 5 × 3 = 15 days. B's: 8 ÷ 2/5 = 20 days. Together 1/15 + 1/20 = 4/60 + 3/60 = 7/60 per day, so 60/7 = 8 4/7 days.
-
4. A, B and C can finish a job in 12, 15 and 20 days. A and B start it, and C joins them after 2 days. How long does the whole job take?
- 5 days
- 5.5 days
- 6 days
- 6.5 days
Show answer
Answer: B. Total = LCM 60 units; A 5, B 4, C 3 a day. In 2 days A and B do 2 × 9 = 18 units, leaving 42. All three do 12 a day: 42 ÷ 12 = 3.5 days. Total = 2 + 3.5 = 5.5 days.
-
5. A can do a job in 8 days and B in 12 days. They work on alternate days, and B works on the first day. In how many days is the job finished?
- 9 1/3 days
- 9 1/2 days
- 10 days
- 9 2/3 days
Show answer
Answer: D. Total = 24 units; A does 3 a day, B 2. Each pair of days gives 5 units, so 8 days (4 pairs) give 20 units. Day 9 is B's: 22 units. Day 10 is A's: he needs 2 of his 3 units, i.e. 2/3 of a day. Total = 9 2/3 days.
-
6. A and B can do a job in 8 days, B and C in 12 days, and A, B and C together in 6 days. How long would A and C take together?
- 8 days
- 10 days
- 12 days
- 24 days
Show answer
Answer: A. C = (A + B + C) - (A + B) = 1/6 - 1/8 = 1/24. A = (A + B + C) - (B + C) = 1/6 - 1/12 = 1/12. A + C = 1/12 + 1/24 = 3/24 = 1/8, so 8 days.
-
7. Pipes A and B fill a tank in 20 and 30 minutes. Both are opened, but B is closed after 6 minutes. How long does the tank take to fill in all?
- 10 minutes
- 12 minutes
- 15 minutes
- 16 minutes
Show answer
Answer: D. Together 1/20 + 1/30 = 5/60 = 1/12 per minute; in 6 minutes they fill 1/2. A fills the other half alone: 1/2 × 20 = 10 minutes. Total = 6 + 10 = 16 minutes.
-
8. An inlet fills a tank in 6 hours and an outlet empties the full tank in 8 hours. Both are opened when the tank is half full. How long until it is full?
- 3.5 hours
- 7 hours
- 12 hours
- 24 hours
Show answer
Answer: C. Net rate = 1/6 - 1/8 = 4/24 - 3/24 = 1/24 per hour. Half a tank is needed: 1/2 × 24 = 12 hours.
-
9. Pipes A and B fill a tank in 12 and 18 hours, and pipe C empties it in 9 hours. If all three are opened on an empty tank, how long does it take to fill?
- 18 hours
- 24 hours
- 36 hours
- 72 hours
Show answer
Answer: C. Net rate = 1/12 + 1/18 - 1/9 = 3/36 + 2/36 - 4/36 = 1/36 per hour. Time = 36 hours.
-
10. 12 men working 8 hours a day finish a job in 10 days. How many men working 6 hours a day are needed to finish it in 8 days?
- 16
- 18
- 24
- 20
Show answer
Answer: D. Total = 12 × 8 × 10 = 960 man-hours. In 8 days at 6 hours a day, each man gives 48 man-hours, so men = 960 ÷ 48 = 20.
-
11. 20 men can build 150 m of road in 15 days. In how many days can 30 men build 240 m?
- 12 days
- 16 days
- 18 days
- 24 days
Show answer
Answer: B. M1 × D1 ÷ W1 = M2 × D2 ÷ W2: 20 × 15 ÷ 150 = 30 × D ÷ 240. Left side = 2, so 30D = 480 and D = 16 days.
-
12. 18 men can finish a job in 25 days. After 10 days, it is decided to finish the job 5 days earlier than planned. How many more men must join?
- 6
- 9
- 12
- 27
Show answer
Answer: B. Total = 18 × 25 = 450 man-days; 180 are done in 10 days, leaving 270. Days left now = 25 - 10 - 5 = 10, so 270 ÷ 10 = 27 men are needed: 27 - 18 = 9 more.
-
13. A is twice as efficient as B, and B is twice as efficient as C. Together they finish a job in 4 days. How long would C alone take?
- 14 days
- 28 days
- 21 days
- 7 days
Show answer
Answer: B. Let C's rate be x; then B = 2x and A = 4x. Together 7x = 1/4, so x = 1/28. C alone takes 28 days.
-
14. A can do a job in 15 days and B in 20 days. With the help of C they finish it together in 6 days and are paid ₹1,200. What is C's share?
- ₹240
- ₹300
- ₹360
- ₹480
Show answer
Answer: C. In 6 days A does 6/15 = 4/10 and B does 6/20 = 3/10, so C did 1 - 7/10 = 3/10. Wages follow work done: C gets 3/10 of ₹1,200 = ₹360.
-
15. A can do a job in 20 days, and B is 25% more efficient than A. They work together for 4 days and then A leaves. How long does B take to finish the rest?
- 8.8 days
- 9 days
- 8 days
- 11 days
Show answer
Answer: A. B's rate = 1.25 × 1/20 = 1/16. Together for 4 days: 4 × (1/20 + 1/16) = 4 × 9/80 = 9/20. Left 11/20, at 1/16 a day: 11/20 × 16 = 8.8 days.
Questions 1-3: lesson 1, "Work done in one day". Questions 4-6: lesson 2, "The LCM method and alternate-day work". Questions 7-9: lesson 3, "Pipes and cisterns". Questions 10-12: lesson 4, "Men, days and hours". Questions 13-15: lesson 5, "Wages, efficiency and mixed problems". Revisit a lesson for the questions you missed.
Sign in to keep track of the lessons you finish.