- Practice
- About 14 min
- 5 practice questions
Men, days and hours
Use the man-days relation M1D1H1/W1 = M2D2H2/W2 and handle workers who join or leave midway.
If something looks wrong, please tell us.
When many workers share a job, think in man-days: the total work equals men × days (and × hours per day if hours are given).
The relation
M1 × D1 × H1 ÷ W1 = M2 × D2 × H2 ÷ W2, where W is the amount of work. If the work is the same, drop W.
Worked example 1
Question: 15 men build a wall in 12 days. How long will 20 men take? Working: Total = 15 × 12 = 180 man-days. 180 ÷ 20 = 9 days. Answer: 9 days.
Worked example 2: hours per day
Question: 8 men work 6 hours a day and finish in 10 days. How many days will 6 men working 8 hours a day need? Working: Total = 8 × 6 × 10 = 480 man-hours. Per day: 6 × 8 = 48. Days = 480 ÷ 48 = 10 days. Answer: 10 days.
Worked example 3: more men join
Question: 12 men can finish a job in 20 days. After 5 days, 6 more men join. In how many days is the job finished in all? Working: Total = 240 man-days. Used in the first 5 days: 60. Left: 180. With 18 men: 180 ÷ 18 = 10 days. Total = 5 + 10 = 15 days. Answer: 15 days.
Total work = men × days (× hours). Subtract what is done, then divide what remains by the new workforce.
Key takeaways: total work in man-days; account for hours if given; and for midway changes, recompute the remaining work.
Check your understanding
-
1. 12 men can build a wall in 15 days. How long will 18 men take?
- 10 days
- 8 days
- 12 days
- 22.5 days
Show answer
Answer: A. Total work = 12 × 15 = 180 man-days. With 18 men: 180 ÷ 18 = 10 days. More men means fewer days.
-
2. 10 men working 6 hours a day finish a job in 12 days. How many days will 8 men working 9 hours a day need?
- 8 days
- 9 days
- 10 days
- 12 days
Show answer
Answer: C. Total = 10 × 6 × 12 = 720 man-hours. Per day the new team gives 8 × 9 = 72 man-hours. Days = 720 ÷ 72 = 10.
-
3. 16 men can finish a job in 30 days. After 10 days, 4 more men join. In how many days in all is the job finished?
- 24 days
- 26 days
- 16 days
- 28 days
Show answer
Answer: B. Total = 16 × 30 = 480 man-days. First 10 days use 160, leaving 320. With 20 men: 320 ÷ 20 = 16 more days. In all: 10 + 16 = 26 days.
-
4. 6 men build a 60 m wall in 10 days. How many men are needed to build a 90 m wall in 5 days?
- 9
- 12
- 18
- 24
Show answer
Answer: C. Use M1 × D1 ÷ W1 = M2 × D2 ÷ W2: 6 × 10 ÷ 60 = M × 5 ÷ 90, so 1 = 5M ÷ 90 and M = 18.
-
5. 15 men can finish a job in 20 days. After 8 days, 5 men leave. How many more days are needed to finish the job?
- 12 days
- 15 days
- 24 days
- 18 days
Show answer
Answer: D. Total = 15 × 20 = 300 man-days. Done in 8 days: 15 × 8 = 120. Left: 180, now for 10 men: 180 ÷ 10 = 18 more days.
Sign in to keep track of the lessons you finish.