- Foundation
- 15 practice questions
Final self-assessment: Time and Work foundation
Test yourself on the whole course: 15 questions with answers explained.
If something looks wrong, please tell us.
Attempt all 15 questions without looking back at the lessons, then check your answers and read each explanation. The questions are a little harder than the checks after each lesson, and several combine ideas from more than one lesson.
Final self-assessment
-
1. A does 2/7 of a job in 4 days. How many more days does he need to finish it?
- 8
- 10
- 12
- 14
Show answer
Answer: B. Rate = (2/7) ÷ 4 = 1/14 per day, so the whole job takes 14 days. Work left = 5/7, which takes 5/7 × 14 = 10 days.
-
2. A can do 3/5 of a job in 12 days. How long does he take to do 1/4 of the job?
- 5 days
- 6 days
- 7.5 days
- 8 days
Show answer
Answer: A. Whole job = 12 ÷ (3/5) = 20 days, so one day's work is 1/20. For 1/4 of the job: (1/4) × 20 = 5 days.
-
3. A can finish a job in 18 days. He works 5 days, rests for 2 days, then works 4 more days. What fraction of the job is left?
- 1/3
- 4/9
- 1/2
- 11/18
Show answer
Answer: C. Only working days count: 5 + 4 = 9 days, doing 9/18 = 1/2. Left = 1 − 1/2 = 1/2. (Counting the rest days gives 11/18 - wrong, since no work is done on them.)
-
4. A, B and C can do a job in 12, 15 and 20 days. Working together, how long do they take?
- 4 days
- 5 days
- 6 days
- 10 days
Show answer
Answer: B. 1/12 + 1/15 + 1/20 = 5/60 + 4/60 + 3/60 = 12/60 = 1/5, so 5 days. (LCM method: 60 units at 5 + 4 + 3 = 12 a day.)
-
5. A and B together can do a job in 8 days. A alone takes 12 days. How long does B take alone?
- 4 days
- 16 days
- 20 days
- 24 days
Show answer
Answer: D. B's rate = 1/8 − 1/12 = 3/24 − 2/24 = 1/24, so B takes 24 days. Together time is always shorter than either worker's own time, so 4 days cannot be right.
-
6. A works twice as fast as B. Together they finish a job in 6 days. How long would A take alone?
- 3 days
- 9 days
- 12 days
- 18 days
Show answer
Answer: B. Let B's rate be x; A's is 2x. Together 3x = 1/6, so x = 1/18. A's rate = 2/18 = 1/9, so A takes 9 days (and B 18 days).
-
7. A, B and C can do a job in 6, 9 and 18 days. Working together, how long do they take?
- 3 days
- 4 days
- 5 days
- 11 days
Show answer
Answer: A. Total = LCM(6, 9, 18) = 18 units. A = 3, B = 2, C = 1 a day, together 6. Time = 18 ÷ 6 = 3 days.
-
8. A takes 12 days and B takes 15 days to do a job. They work together for 4 days, then A leaves. How many more days does B need?
- 4
- 5
- 6
- 8
Show answer
Answer: C. Total = LCM(12, 15) = 60 units; A = 5, B = 4 a day. In 4 days together: 4 × 9 = 36 units, leaving 24. B does 4 a day, so 6 more days.
-
9. A, B and C can do a job in 10, 12 and 15 days. All three work for 2 days, then B leaves and A and C finish the job. How many days does the job take in all?
- 3
- 4
- 4.5
- 5
Show answer
Answer: D. Total = 60 units; A = 6, B = 5, C = 4 a day. In 2 days all three do 2 × 15 = 30 units. A and C do the remaining 30 at 10 a day in 3 days. Total = 2 + 3 = 5 days.
-
10. A takes 8 days and B takes 12 days. They work on alternate days, starting with B. On which day is the job completed?
- Day 9
- Day 10
- Day 11
- Day 12
Show answer
Answer: B. Total = 24 units; A = 3, B = 2. Each two-day cycle does 5, so 4 cycles (8 days) do 20 units, leaving 4. Day 9 (B) adds 2, leaving 2. Day 10 (A) can do 3, so the job is completed during day 10.
-
11. A takes 12 days and B takes 18 days. They start together, but A leaves 3 days before the job is finished. How long does the job take?
- 7 days
- 8 days
- 9 days
- 10 days
Show answer
Answer: C. Total = 36 units; A = 3, B = 2. B works x days and A works (x − 3): 2x + 3(x − 3) = 36, so 5x = 45 and x = 9. Check: B 18 + A 6 × 3 = 18, total 36.
-
12. A and B together can do a job in 15 days. After 6 days B leaves, and A finishes the rest in 18 days. How long would A take alone?
- 30 days
- 32 days
- 36 days
- 45 days
Show answer
Answer: A. In 6 days together they do 6/15 = 2/5, leaving 3/5. A does 3/5 in 18 days, so the whole job takes A 18 × 5/3 = 30 days.
-
13. 16 men can finish a job in 21 days. After 6 days, 4 men leave. How many more days are needed?
- 15
- 18
- 20
- 24
Show answer
Answer: C. Total = 16 × 21 = 336 man-days. Done in 6 days: 96. Left: 240 man-days with 12 men, so 240 ÷ 12 = 20 more days.
-
14. Pipes A and B fill a tank in 12 and 15 hours; pipe C empties a full tank in 20 hours. With all three open, how long does the empty tank take to fill?
- 5 hours
- 6 hours 40 minutes
- 8 hours
- 10 hours
Show answer
Answer: D. Net rate = 1/12 + 1/15 − 1/20 = 5/60 + 4/60 − 3/60 = 6/60 = 1/10, so 10 hours. (6 hours 40 minutes forgets the outlet.)
-
15. A, B and C can do a job alone in 6, 8 and 12 days. Working together they finish it and are paid ₹1,800. What is C's fair share?
- ₹400
- ₹450
- ₹600
- ₹800
Show answer
Answer: A. Share by work done. With total = 24 units, daily work is A 4, B 3, C 2, a ratio of 4 : 3 : 2. C gets 2/9 of 1,800 = ₹400.
Which lesson to revisit: questions 1-3: lesson 1, "Work done in a day: the basic idea"; questions 4-6: lesson 2, "Working together"; questions 7-9: lesson 3, "The LCM method: work in units"; questions 10-12: lesson 4, "Alternate days and leaving the work midway"; questions 13-15: lesson 5, "Man-days, wages and pipes". If you missed two or more questions from one lesson, work through that lesson's examples again before moving on.