Comparing energy sources fairly needs more than rated power. A 1 MW solar plant and a 1 MW hydro plant do not produce the same energy in a year, and they do not cost the same per unit. Three ideas let you compare them: capacity factor, efficiency chains and levelised cost. They often appear together in one longer question, so this lesson builds them in order and then combines them.
Capacity factor, both directions
Capacity factor (CF) is actual yearly energy divided by rated power times 8,760 hours. Rearranged, yearly energy = rated power × 8,760 × CF. A useful speed fact: 1 MW running all year gives 8,760 MWh, so a plant of P MW with capacity factor CF gives P × 8,760 × CF MWh. Solar plants tend to have lower capacity factors than geothermal plants, because sunlight is absent at night while geothermal heat is steady; never treat a capacity factor as the same thing as efficiency.
Yearly energy = Rated power × 8,760 h × Capacity factor. Capacity factor is about time at full output; efficiency is about conversion losses.
The difference matters. A solar panel's efficiency (say 20%) is the share of sunlight turned into electricity at any moment. Its capacity factor (say 18%) is how its yearly output compares with running at rated power around the clock. They are different numbers that happen to look similar.
Efficiency chains
Energy often passes through several steps, each losing some. The overall efficiency is the product of the step efficiencies, never the sum or the average. A turbine at 90%, a generator at 95% and a transformer at 98% give 0.90 × 0.95 × 0.98 = 0.8379, about 83.8%. A long chain of quite good steps can still lose a lot: five steps of 90% each give 0.9⁵ ≈ 0.59.
Levelised cost of energy
The levelised cost of energy (LCOE) is the average cost of each unit of electricity over a plant's whole life. In its simplest form it is total lifetime cost divided by total lifetime energy. Total cost includes the upfront building cost, operation and maintenance, and fuel; solar and wind have no fuel cost but a high upfront cost, while a gas plant has a lower upfront cost but pays for fuel throughout its life. In full analyses future costs and energy are discounted, because money today is worth more than money later, but the core idea is the ratio.
Simple LCOE = Total lifetime cost ÷ Total lifetime energy. Higher capacity factor spreads the same cost over more energy and lowers the LCOE.
Worked example 1: yearly energy
A 50 MW wind farm has a capacity factor of 35%. Yearly energy = 50 × 8,760 × 0.35. 50 × 8,760 = 438,000 MWh; × 0.35 = 153,300 MWh. If a question then asks for the average power over the year, divide by 8,760: 153,300 ÷ 8,760 = 17.5 MW, which is simply 50 × 0.35.
Worked example 2: a simple LCOE
A small solar plant (illustrative numbers) costs ₹40 lakh to build and ₹10 lakh in total maintenance over a 20-year life. It produces 25,000 kWh a year. Total cost = ₹50 lakh = ₹50,00,000. Lifetime energy = 25,000 × 20 = 5,00,000 kWh. LCOE = 50,00,000 ÷ 5,00,000 = ₹10 per kWh. If better siting raised output by 25% to 31,250 kWh a year, the lifetime energy would be 6,25,000 kWh and the LCOE 50,00,000 ÷ 6,25,000 = ₹8 per kWh.
Worked example 3: putting it together
A 2 MW solar plant has a capacity factor of 20% and its inverter is 97% efficient; the capacity factor given is measured before the inverter. Energy before the inverter = 2 × 8,760 × 0.20 = 3,504 MWh. After the inverter = 3,504 × 0.97 = 3,398.88 MWh, about 3,399 MWh. Work step by step and state which loss each step includes.
Key takeaways
Yearly energy = rated power × 8,760 × capacity factor; capacity factor and efficiency are different ideas. Chain efficiencies multiply. LCOE is lifetime cost divided by lifetime energy; raising output with the same cost lowers it, and full calculations discount future amounts.
Check your understanding
-
1. A 10 MW plant has a capacity factor of 40%. How much energy does it produce in a year?
- 87,600 MWh
- 4,000 MWh
- 21,900 MWh
- 35,040 MWh
Show answer
Answer: D. 10 × 8,760 = 87,600 MWh at full power; × 0.40 = 35,040 MWh.
-
2. Three steps in a chain have efficiencies of 80%, 90% and 50%. What is the overall efficiency?
- 73.3%
- 36%
- 220%
- 50%
Show answer
Answer: B. Multiply: 0.8 × 0.9 × 0.5 = 0.36 = 36%.
-
3. Which statement best describes capacity factor?
- The share of sunlight a panel turns into electricity
- The maximum share of wind power a turbine can capture
- Actual energy produced compared with running at rated power all the time
- The cost of each unit of electricity over the plant's life
Show answer
Answer: C. Capacity factor compares actual energy with rated power × hours. Conversion share is efficiency, the wind maximum is the Betz limit, and the cost per unit is LCOE.
-
4. A plant costs ₹60 lakh in total over its life and produces 4,00,000 kWh in that time. What is its simple LCOE?
- ₹6.67 per kWh
- ₹1.5 per kWh
- ₹150 per kWh
- ₹15 per kWh
Show answer
Answer: D. LCOE = 60,00,000 ÷ 4,00,000 = ₹15 per kWh.
-
5. With all costs unchanged, a plant's yearly output rises by 25%. Its simple LCOE becomes:
- 125% of its old value
- 80% of its old value
- 75% of its old value
- unchanged
Show answer
Answer: B. LCOE = cost ÷ energy. Energy × 1.25 means LCOE × 1/1.25 = 0.8, i.e. 80% of the old value, a 20% fall.